第一章 主要施工方案及重大技术措施
第一节 土建
1 方格网布设及沉降观测方案
1.1 方格网布置:
根据厂区总平面布置图、厂区地下设施布置图和施工总平面布置图,确定平面及高程控制桩的布设图。布设原则遵循从高级到低级、从整体到局部的原则。要求相邻点通视良好,视线离开障碍物一定距离,并便于扩展和加密。定出主厂房的主轴线,根据这些主轴线建立主厂房轴线控制网。高程控制网分两级,首先沿厂区方格网点布设二等水准网,作为整个施工场地的高程控制网,然后根据厂区高程控制网布设主房高程控制点。布设时还要考虑新老厂房的连接,并测出#1、#2机厂房相关数据,供施工时加以调整,以保证新老厂房平面和竖向的一致性和连接精度。
1.2 方格网桩位埋设:
桩的形式为400×400现浇钢筋混凝土桩,桩位埋设深度80cm,桩顶埋设200×200的不锈钢标志板,上焊φ10不锈钢半球,桩位埋设完毕后四周用脚手管围栏加以保护。
1.3 仪器:
方格网采用瑞士雷卡TC—1800(2mm+2ppm,1.5")智能型全站仪(此仪器是我公司唯一拥有目前国内施工单位最先进的仪器)进行测设,测设精度为边长ms≤s/40000,测角精度mβ≤±⒉5″。高程控制网的测设采用德国FG005A精密水准仪配铟瓦水准尺按二等水准测量规范实施,平差后的
The first chapter is a major construction program and technical measures
Civil Section
A square grid layout and settlement observation program
1.1 Grid layout:
According to plant general layout plans, plant layout and construction of underground facilities, the general layout plan to determine the Horizontal and Vertical Control pile layout plan. Follow the principles laid from high to low, from whole to parts and principles. Adjacent points, as requested through a good sight distance from obstacles, and facilitate expansion and encryption. Set the main building's main axis, according to the axis of the main axis of the establishment of the main plant control network. Elevation control network at two levels, first of all network laid along the second level of the box factory network, as the construction site of the control network, and plant height control network according to the main room elevation control points. Layout must be considered when connecting the old and new plants and measured # 1, # 2 machine factory data for the construction to be adjusted to ensure that new and old plant flat and vertical accuracy of the consistency and connectivity.
1.2 Grid Pile laying:
Pile in the form of 400 × 400 cast reinforced concrete piles, Pile laying depth 80cm, 200 × 200 laid pile top stainless steel logo plate, the welding of stainless steel hemisphere φ10, Pile laying around after the hand-foot pipe fence to protect them.
1.3 Instrument:
Grid using Ruishileika TC-1800 (2mm +2 ppm, 1.5 ") Intelligent Total Station (This instrument is the sole owner of the company's most advanced domestic equipment construction unit) to survey and design, test set accuracy of edge long ms ≤ s/40000, angular accuracy mβ ≤ ± ⒉ 5 ". Elevation control networks established by the German FG005A with indium-watt standard of precision leveling feet standard implemented by second-class standard of measurement, after adjustment