一、 施工准备
(一) 作业条件
1、 墙体结构已弹出施工水平线。
2、 安装配电箱所需的木砖及铁件巳预埋。
3、 随土建结构预留的暗装配电箱的安装位置正确,大小合适。
暗装配电箱箱体时,安装箱体墙面的抹灰应全部完成。暗装配电箱盘
First, construction preparation
(A) Operating conditions
1, pop-up construction of the wall structure is horizontal.
2, the required distribution box installed wood brick and iron pieces had embedded.
3, with the civil engineering structure of the dark assembly reserved for the installation of electrical boxes in the correct position, the right size.
Electrical box assembly dark box, the installation of the plaster wall box should be completed. Disc dark electric box assembly