配电箱安装施工要点

(1)设备要求
1)柜(盘)本体外观检查应无损伤及变形,油漆完整无损。柜(盘)内部检查:电器装置及元件、绝缘瓷件齐全,无损伤、裂纹等缺陷。
2)安装前应核对配电箱编号是否与安装位置相符,按设计图纸检查其箱号、箱内回路号。箱门接地应采用软铜编织线,专用接线端子。箱内接线应整齐,满足设计要求及验收规范(GB50303-2002)的规定。
(2)作业条件
配电箱安装场所土建应具备内粉刷完成、门窗已装好的基本条件。预埋管道及预埋件均应清理好;场地具备运输条件,保持道路平整畅通。
(3)配电箱定位:根据设计要求现场确定配电箱位置以及现场实际设备安装情况,按照箱的外形尺寸进行弹线定位。
(4)基础型钢安装
1)按图纸要求预制加工基础型钢架,并做好防腐处理,按施工图纸所标位置,将预制好的基础型钢架放在预留铁件上,找平、找正后将基础型钢架、预埋铁
Distribution box installation and construction elements

(1) Equipment requirements
1) cabinet (disk) visual inspection body should be no damage and deformation, paint intact. Cabinet (disk) internal inspection: electrical equipment and components, complete insulation porcelain pieces, no damage, cracks and other defects.
2) Before installation should check whether the distribution box number in line with the installation location, according to design drawings check the box number, box number loop. Door ground should be soft copper braided wire, special terminal. Box wiring should be neat to meet the design requirements and acceptance (GB50303-2002) requirements.
(2) Operating conditions
Distribution box installation sites within the civil engineering should have completed painting, doors and windows have been installed good basic conditions. Embedded pipe and embedded parts shall be cleared; site with transportation to keep the flow smooth.
(3) distribution box Location: According to the design field position and field distribution box to determine the actual installation conditions, according to box dimensions for bomb line orientation.
(4) basic steel installation
1) The requirements of the drawings based on pre-processing of steel frame, and good corrosion protection, construction drawings are marked by location, type of prefabricated steel frame on the basis of a good reserve iron, the leveling, aligning steel frame will be based, pre- Underground Railway
 