管道安装作业指导书.pdf
管 道 敷 设
一、沟槽开挖
1、管道沟槽的开挖应按照图纸所提坐标位置和标高进行,不允许挖到设计标高以下。
2、管槽施工开挖前要在距堑顶10m以外设临时截、排水沟,沟内挖的土在路堑与沟之间修成土台并夯实,台顶筑成2%倾向截水沟的横坡。临时排水设施尽量与永久性排水设施相结合,把水及时排到自然沟,避免对路基产生危害。
3、沟槽的开挖边坡应按图纸要求。
4、开挖时,若遇到雨季或流砂,可酌情加大边坡或用挡板支撑。
5、管道基础在开挖时发现人工土、淤泥、或流砂,必须同时设计单位进行处理。
6、沟槽的开挖底宽须满足管外壁与沟底边线
Pipe laying
1, trench excavation
1, pipe trench excavation shall be made in accordance with coordinates of the location and elevation drawings were not allowed to excavate the following design elevation.
2, ducts before excavation cut in from the top 10m to peripheral temporary cut, drain, ditch digging the soil in the cutting and communication platform between the marble and soil compaction, built into the top 2% of Taiwan tend to ditch the cross-sectional slope. Permanent temporary drainage facilities, drainage facilities as far as possible with the combination of the water discharged to the natural channel in time to avoid harm to the subgrade.
3, trench excavation slopes should be drawings.
4, excavation, when the rainy season or the flow of sand, can increase the slope or baffle appropriate support.
5, when the pipe was found in the excavation based on artificial soil, silt, or sand, must also design units for processing.
6, the excavation trench bottom width to satisfy the exterior and ditch edges
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154873次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139022次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90906次
- CAD2008注册机及使用说明
- 84341次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 给水排水构筑物施工及验收规范GBJ141-9
- 1513次
- 给排水管道通水试验记录
- 931次
- 给水排水通用图集(CAD)
- 858次
- 建筑给水排水设计规范GB50015-2003
- 830次
- 共板法兰风管制作安装工艺
- 793次
- 给水排水及采暖工程报验用表列表
- 750次
- 建筑给排水及采暖工程施工质量验收资料
- 575次
- ***室外排水管道施工方案
- 570次
- 水泵扬程估算方法
- 569次
- 给排水工程施工组织设计方案
- 530次