一、 施工准备阶段监理控制要点
1、施工单位必须具备相应专业资质,并应建立完善的质量管理体系和质量检验制度。监理尚应审核专职管理人员、特种作业人员资格证、上岗证。
2、审核承包单位报送的开工报审表、施工方案和施工组织设计报审表。
3、审核承包单位报送的施工测量成果及施工测量成果报验表。复查桩位、控制标高等,桩位允许偏差,群桩20mm,单桩10mm。
4、审核承包单位报送的进场工程材料质量证明资料和报审表,如为成品钢桩,应符合成品桩的质量标准表的规定
1, construction supervision control of the preparatory phase
1, the construction unit must have appropriate professional qualifications, and should establish a sound quality management system and quality inspection system. Supervision there should be full-time management audits, and special operations personnel qualification certificates, appointment cards.
2, review contractor reports submitted by the trial started the table, the construction program and construction organization design report review form.
3, reviewed the construction contractors to submit construction survey results Survey results and inspection tables. Review pile and control the elevation, etc., to allow deviation Pile, pile 20mm, Pile 10mm.
4, approved contractors entering engineering materials submitted by the quality of supporting information and approval of forms, such as a pile of finished steel, finished pile shall meet the requirements of quality standards table
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160636次
- Autocad2013 64位32位破解版附带注册机
- 148338次
- 天正建筑8.5破解版
- 144064次
- autocad2012 64位32位 破解版(附注册
- 137474次
- 天正建筑8.2破解版
- 123404次
- autocad2010免费下载(简体中文版)
- 97153次
- CAD2008注册机及使用说明
- 80821次
- 免费农村房屋设计图
- 73777次
- cad图集大全
- 56848次
- 11g101图集全套下载
- 45449次
- 安全监理细则
- 1297次
- 安全监理实施细则(范本)
- 927次
- 船台监理细则
- 634次
- 安全监理实施细则
- 630次
- 基坑锚杆及土钉墙支护工程监理要点(细
- 571次
- 深基坑开挖工程施工质量监理细则
- 515次
- 武广客运专线武汉至花都工程JL2标后张
- 477次
- 砖混结构监理细则
- 459次
- 免费安全文明施工监理实施细则
- 437次
- 绿化工程监理实施细则
- 436次