一、 前言Preface
污水提升泵站压密注浆主要针对其基坑底板下部的约1.8m厚的粉土,因其底板呈阶梯部,部份土体滑动,造成部份底板与其下部粉土的分离,而形成空洞,目前通过现场勘察,因破坏处为16×3×1.8m。因而要求采用注浆方式进行土体加固。This plan is mainly aimed at about 1.8m THK powder soil in the bottom slab of foundation pit. As the bottom slab is in a step and part of the soil is slided, some slabs are separated from the powder soil. So the hollows turn up. After the site investigation, as the broken area is 16*3*1.8m, method of grouting should be adopted for the soil strengthening.
二、 压密注浆方法Methodology for Compaction and Grouting
该工程基坑底板现已浇注成功,依据现场的破坏程度及以往的施工经验,先通过人工方式在底板开孔,然后依据水灰比0.5~0.6的方案进行搅拌水泥浆,再将搅拌均匀的水泥浆用机械方式输入孔洞中,已达到加固地基土为目的。The bottom slab in foundation pit has been successfully placed. According to the damage degree and our construction experience, firstly we will make hole by manpower, secondly mix cement mortar in a water cement ratio of 0.5~0.6. Then cement mortar will be conveyed into holes by machine to meet the requirement.
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173181次
- Autocad2013 64位32位破解版附带注册机
- 154619次
- 天正建筑8.5破解版
- 146319次
- autocad2012 64位32位 破解版(附注册
- 138878次
- 天正建筑8.2破解版
- 127146次
- autocad2010免费下载(简体中文版)
- 98090次
- 免费农村房屋设计图
- 90315次
- CAD2008注册机及使用说明
- 84227次
- 11g101图集全套下载
- 77800次
- cad图集大全
- 67202次
- 全套教学楼毕业设计
- 2500次
- 5号、4A号砖砌化粪池施工方案
- 2080次
- 施工围墙施工方案
- 1692次
- 后浇带施工方案
- 1460次
- 悬挑式脚手架施工方案
- 1403次
- 冬季施工应急预案
- 1209次
- 大型机械土石方平整工程施工方案
- 1196次
- 现场安全文明施工方案
- 1143次
- 悬挑卸料平台搭设方案及计算
- 1122次
- 楼梯踏步护角做法(CAD)
- 1087次