1.工程概况
第29届奥运会青岛国际帆船中心陆域建筑Ⅱ标段奥运村工程位于燕儿岛路1号,本工程裙房四层(局部一层),裙房以上托两个17层高层建筑和两个7层多层建筑共四个单体工程,地上一层层高6米,二层层高5米,三层及以上层高3.5m,地上建筑面积58921m2,含二层地下室总建筑面积为89296m2,两个17层建筑总高度为77.116米,两个7层建筑总高度为30.9米。
2.外脚手架搭设方案选择
根据本工程的特点,主要考虑在主体施工期间及装修阶段的安全防护,保证工程顺利进行,设计使用外脚手架的施工搭设方案:
裙房四周及主楼无裙房的部位采用落地式双排扣件式钢管脚手架搭设方案,两个17层高层施工过程中设两道悬挑外脚手架,分别从主楼6层顶和13层顶开始设置,两个7层建筑采用落地式双排脚手架。脚手架均为全封闭封圈形,以密目安全网在脚手架外排内侧封闭。脚手架内侧立杆离外墙面≤350㎜,立杆横向间距900㎜,纵向间距1800㎜,大横杆步距1800㎜,操作层1. Project Overview
29th Olympic Games in Qingdao International Sailing Center Land Building Ⅱ Olympic Village project is located at Lot 1, Majoring in Island Road, the project podium four (local level), skirt over care of two 17 storey buildings and two 7 layer multi-layer construction of four single projects on the ground floor storey 6 meters, 5 meters in the second floor storey, three storey above 3.5m, ground floor area of 58921m2, two-story basement with a total construction area of 89296m2 , two 17-storey building total height of 77.116 meters, two 7-story building total height of 30.9 meters.
2. External Scaffolding Selection
According to the characteristics of this project, the main considerations during the construction and decoration in the main phase of the security, to ensure the smooth progress of projects, designed for use outside the construction scaffold erection program:
Skirt around the podium and main building of the site without using double-breasted floor piece Scaffolding program, two 17-story high-rise construction in the scaffolding set up outside two cantilever, respectively, from the main building of 6 floors and 13 floor roof top of the beginning set, two 7-story building with floor double scaffold. Scaffolding are completely closed seal ring-shaped head to close a safety net efflux in the medial scaffold closed. Scaffolding outside the wall from the inside pole ≤ 350 mm, pole spacing of 900 mm horizontal and vertical spacing of 1800 mm, 1800 mm away from the big bar step, the operation level

 