五、防水工程施工方案.doc
地下室底板平面面积约××m2,分为六块,间有伸缩缝5条,伸缩缝宽度7cm。地下室负二层,底板到±0.000为6m,立面面积约为××m2。
3、施工进度
×月×日开始施工,到×月×日底板施工完毕,立面施工到保护墙等同高度、其余立面随土建混凝土墙面进度进行。
4、施工准备
4.1施工面的水混找平层应压平抹光,坚实平整,含水率≤90%,以保证材料粘贴牢固。
4.2底板平面涂一遍冷底油,干燥4小时。
5、劳动组织
Basement surface area of about × × m2, divided into six blocks, there are expansion joints between 5, expansion joint width 7cm. Negative two-story basement, floor to ± 0.000 for the 6m, elevation area of about × × m2.
3, construction progress
× month × day construction, to × month × date base construction completed, the elevation of the wall construction to protect the same height, the other elevations of concrete wall with the progress of civil works.
4, construction preparation
4.1 Construction of surface water mixed layer should be compacted leveling trowel, a solid formation, water content ≤ 90%, in order to ensure a solid material paste.
4.2 cold floor flat again coating base oil, dry 4 hours.
5, the labor organization
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次