十二、暖通工程施工方案.doc
1、暖通工程概况
该工程一至十六层为研究、实验、办公部分,通风空调采用风机盘管加新风系统,每层设2台新风机组,B1层为设备部分,内设空调机房,采用大风道系统南北各设轴流风机1台。
2、施工组织
2.1 劳动组织准备:本工程的总包方为北京××建设工程有限责任公司第××项目经理部,机电设备部分分包给北京××公司水电分公司,在总包方统一领导下开展工作,针对新承包的工程项目,配备相应施工人员,建立施工管理体生活费,对工程进度,质量进行严格控制,保证施工顺利进行,各专业、项目设有专业人员专业管理。
2.2 技术准备:组织技术人员熟悉施工图纸和有关的设计资料,对相关的技术、经济和自然条件进行调查分析、研究可行的施工方案。针对图纸中存在的问题及时记录,为施工作出准确的、科学的技术指导。
2.3施工现场准备:施工道路、施工用水、施工用电和加工场地由总包方统一规划,生产、办公、生活用房等临时用房由总包方提供。
2.4本专业空调系统由施工班组加工、制作、安装、保温,根据专业
1, HVAC Engineering Overview
The six works from 1 to 10 for research, experiment, office parts, ventilation and air conditioning with air fan coil system, 2 sets of each floor of new air unit, B1 floor for equipment parts, equipped with air-conditioned room, with strong winds located north and south of Road System axial fan 1 set.
2, construction organization
2.1 The labor organization and preparation: The project's general contractor for the construction of Beijing × × × × a limited liability company's first project management department, the mechanical and equipment to the Beijing × × sub-division of water and electricity, the total package to work under the unified leadership of party for the new contracted projects, with appropriate construction personnel, construction management body set up cost of living, on the progress of the project, strict quality control to ensure the smooth construction, professional, project management with professional expertise.
2.2 Technical Preparation: Organization and technical personnel familiar with the construction drawings and related design information on the relevant technical, economic and natural conditions of investigation and analysis of viable construction plan. Problems for drawing time record for the construction of an accurate, scientific technical guidance.
2.3 to prepare the construction site: Construction of roads, construction of water, electricity and construction of processing facilities by the total package side of unified planning, production, office, living rooms and other temporary buildings provided by the total package.
2.4 The professional air conditioning system consists of the construction team processing, production, installation, insulation, according to professional
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次