3.施工部署
根据现场场地及施工安排,基槽开挖及边坡护壁于11月上旬结束,下一步(冬施)将进行垫层施工及基础施工。
3.1  施工准备
3.1.1  冬季施工时间:日平均气温连续5天低于5℃或11月15日,为冬施开始日期;日平均气温连续5天高于5℃或3月15日,为冬施工结束日期。现场应于11月初即开始对大气进行测温,上述两个条件有一个达到即确定为冬施的起、止日期。
3.1.2  根据目前的施工情况,熟悉掌握各部位施工方法,合理安排施工进度,保证把各种费用降到最低点。
3.1.3  通过计算并结合工程特点,根据初冬(11月15日一12月15日)和严冬(12月15日一次年2月底以大气温度不低于—10C为标准)各时期的气温,选用合理的添加剂和保温措施。
3.2  现场准备
3.2.1  根据施工进度计划,材料部门提前组织有关机具、外加剂和保温供暖设备、材料的进场。
3.2.2  对各种加热的设备、保温材料仔细检查其安全可靠性。
3.2.3  工地临时供水管道做好保温防冻工作。
3. Construction of the deployment
Site and construction of the arrangement according to the site, excavation and foundation trench slope Wall in November ended early, the next step (in winter) will be cushion construction and foundation construction.
3.1 Construction of preparation
3.1.1 construction in winter time: daily average temperature below 5 ℃ for 5 days, or November 15 for winter construction start date; daily average temperature above 5 ℃ for 5 days or 15 March, the end date of construction for the winter . Site should be started early in November that the atmosphere temperature, the above two conditions have a reach that is identified as starting in winter, only the date.
3.1.2 Under the current construction of the mastery of each part of the construction methods, construction progress and reasonable arrangements to ensure that the various expenses to a minimum.
3.1.3 by calculation and engineering characteristics, according to early winter (Nov. 15 1 Dec. 15) and winter (December 15 by the end of February to the first years of atmospheric temperature not lower than-10C as standard) the period of the temperature, reasonable use of additives and thermal insulation measures.
3.2 site preparation
3.2.1 According to the construction schedule, materials, organization of department equipment in advance, additives, and thermal heating equipment, materials, approach.
3.2.2 on a variety of heating equipment, insulation materials, double-check their safety and reliability.
3.2.3 temporary water supply pipeline construction site work well frost insulation.
 