十九、现场消防保卫措施.doc
1、工程概况
北京××科研实验大楼工程位于北京市××区××路××号,总建筑面积29052m2,地下二层,地上十六层,结构型式为全现浇框架—简体结构,建筑物檐高59.65m,总高65.40m。
该工程施工现场狭小,现场内设办公用房和钢筋加工厂、木工棚、成品、半成品及周转材料堆放区域等,将民工生活区设在现场以外。
该工程工期630天(打桩降水除外)。
该工程处于北三环与北四环之间,南临××路,为保障施工顺利进行,特将消防保卫放在重点地位,而制订该方案。
2、施工现场消防保卫情况分析
根据现场临设及施工现场情况,预计本工地消防、保卫重点部位有如下几处,为使工地达到市级文明现场的目标,确保不出现火灾及失窃等事故,特将这几处重点危险区提名到案,加强在施工中的管理。
(1)北京××科研实验大楼工程属全现浇框架一筒体结构高层建筑,施工过程中木材用量较大,大部分施工人员为民工,由于民工对消防知识懂得较少,防火意识差,思想容易麻痹,不定时会出现民工在现场违章吸烟情况,以及施工中的电焊焊花溅落容易发生火灾。
(2)现场临设材料库、油库和油料存放处等地方油类、漆类、易
1, Project Overview
Beijing × × research laboratory building project in the District, Beijing × × × × × × Road, with a total construction area of 29052m2, basement level, ground 16 level, full-cast frame structure type - simplified structure, building eaves high 59.65 m, total height 65.40m.
Narrow construction of the project site, on-site office space and equipped with steel plants, wood sheds, finished products, semi-finished and working materials such as stacking area will be set up in a migrant workers live outside the scene.
The project duration 630 days (other than piling precipitation).
The project is between the North Third Ring Road and North Fourth Ring Road, south × × Road, for the protection of the smooth construction, special emphasis will be placed on the status of fire protection, and development of the program.
2 Analysis of the construction site fire protection
Temporary site design and construction according to the scene, it is expected the fire site, there are several key positions to defend, for the site to achieve the goal municipal civil site, ensure there is no fire and theft and other incidents, especially these few key risk areas nomination in custody, the strengthening in construction management.
(1) × × Beijing research laboratory building project is a tube structure of the whole cast frame high-rise building, a larger amount of wood during construction, most construction workers for the workers, because workers know little knowledge of fire, fire safety awareness of poor Thought easy paralysis, irregular migrant workers in the field illegally will appear smoking, and construction welding welding fire flower splashed down easily.
(2) on-site temporary library set up materials, oil tanks and oil storage areas and so the local oil, paint, easy
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次