二十三、成品保护措施方案.doc
1、玻璃幕墙、铝合金窗成品保护措施
(1)幕墙、窗框四周嵌防水密封胶时,操作应仔细,不得污染幕墙、窗框。
(2)拆搭脚手架、跳板其材料对铝框要有相应的保护措施,否则不许在门窗框上拖拽,安装管线,设备应防止撞坏幕墙。
(3)不许在幕墙、窗框上撞击,钉钉或刻划,幕墙、窗玻璃安装后立即贴上“小心玻璃”标志。
2.电信通成品保护
面板、模块、配线架、机柜、控制箱、控制柜、摄像头和报警器的安装在内装基本完成后进行。其他安装与相关工序配合进行。 3、钟馗门业成品保护措施
(1)木门扇、框及贴脸线和筒子板等进入场地后,必须将材料放置在通风良好,防雨防潮的地方并设专人管理。
(2)油漆和胶等一些易燃材料必须放置在远离火种和易燃产品处,并设专用房间加以保管。
(3)产品在油漆和安装完后,将产品用塑料布将油漆好的产品全部遮盖起来,以免其它杂质对本产品的污染。
(4)严禁撞击门框扇及贴脸。
4、地面、墙面成品保护措施
(1)地面抹好后,进行洒水养护七天内不得进行下一道工序操作。
(2)运输通道处的地面,养护完毕后铺设保护层保护地面。
(3)做好的地面,不允许有污染物落洒在地面上如:机油、油漆、油污、胶或粘结剂,更不能在水泥地面上拌合砂浆。
1, glass curtain walls, aluminum windows product protection
(1) walls, embedded waterproof sealant around window frames, the operation should be careful not to pollute the walls, window frames.
(2) dismantling scaffolding, a springboard for its material on the aluminum frame should have the appropriate protection measures, or not allowed to drag on the door window frame, install pipes and equipment should be prevented from crashing wall.
(3) not allowed in the walls, window frames on the impact, nails, or carved, walls, windows installed immediately labeled "glass with care" signs.
2. Telecom through final product
Panel, modules, patch panels, cabinets, control boxes, control box, camera and alarm devices installed in the interior after the basic completion. Installation and associated with other processes carried out. 3, Zhong Kui Doors product protection
(1) wood door, frame and cheek lines, and the cheese board to enter the venue, the material must be placed in well-ventilated, rain and moisture management where the designated persons.
(2) paint and plastic and other flammable materials must be placed in the fire and flammable products away from the office and set up special rooms to be kept.
(3) and installation of finished products in the paint, paint products to use plastic sheeting to cover up all the good products, so as to avoid other impurities contamination of the product.
(4) non-impact door fan and cheek.
4, floor, wall protection product
(1) the ground after a good wiping, spraying water conservation for the next seven days not a process action.
(2) Transportation Corridor Agency's ground, after the laying of the conservation protection layer to protect the ground.
(3) the ground do not allow for contaminants spilled on the ground down such as: oil, paint, grease, glue or adhesive, but not mixing mortar in the concrete floor.
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次