XX师范学院东院教职工住宅楼(C栋)工程投标施工方案.doc
一 施 工 方 案
编制依据:XX师范学院东院教职工住宅(C栋)设计施工图纸
XX师范学院东院教工住宅(18、19栋)工程招标书
招标答疑
建筑工程施工及验收规范
本公司施工经验
现场实际情况
1. 1、工程概况
本工程为XX师范学院东院教职工住宅楼(C栋)工程。位于XX市XX师范学院生活区院内,由XX设计有限责任公司设计。建筑面积为5497.7m2,其中四室两厅共36套,每套152.7m2,复式砖混结构,共三个单元,总长为73.54m,宽为14.94m,标准层:六层,层高均为2.80m,架空层为杂物间及车库,层高分别为1.95m和2.55m,檐口高度为18.99m和19.25m。
1.1.1、建筑概况
本工程为三个单元呈一字型平面布置,每户由四室二厅一厨二厕二阳台组成。
1 、楼地面:
客厅、卧室、餐厅、阳台、楼梯间地面为水泥砂浆压光,厕、厨为250×250防滑地砖楼面。贮藏间为60mm厚砼地面,水泥砂浆面层,楼梯间踢脚线为水泥砂浆踢脚线。
2 、内墙面、天棚:
所有天棚均为为水泥砂浆打底,“904”仿瓷涂料三遍。 厕所、卫生间内墙为水泥砂浆打底,面层200×300面砖到顶。其余内
A work plan was implemented
Prepared according to: XX Normal University East Hospital Staff Housing (C Building) design and construction drawings
XX Normal University East Hospital faculty housing (18,19 Building) project tender
Tender Q
Building construction and acceptance
The company's construction experience
The actual situation on site
1.1, Project Overview
This works for the XX Normal University East Hospital Staff Residence Building (C Building) project. XX XX City Teachers College in living area hospital, a limited liability company by the XX design design. Construction area 5497.7m2, which Sishiliangting 36 sets, each set of 152.7m2, double-brick structure, a total of three units, a total length of 73.54m, a width of 14.94m, the standard level: six, floors are 2.80m, elevated floor utility room and garage floors were 1.95m and 2.55m, eaves height of 18.99m and 19.25m.
1.1.1, building profiles
This project was a font for the three units layout, household toilets by the Sishierting a kitchen and second balcony second component.
1, the ground floor:
Living room, bedroom, dining, balcony, staircase light ground pressure for the cement mortar, toilet, kitchen floor to 250 × 250 Fanghuadizhuan. Storage rooms for the 60mm thick concrete floors, cement mortar surface, stair baseboard skirting board for the cement mortar.
2, internal walls, ceiling:
All of cement mortar for the ceiling are bottoming, "904" three times melamine coating. Toilet, bathroom walls for the cement mortar primer, the surface layer 200 × 300 tile up to the ceiling. Remaining within
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次