XX乡人民政府综合楼施工方案.doc
一、施工方案
1.1 工程概况
(1) 工程名称:XX乡人民政府综合楼
(2) 工程地点:XX乡人民政府院内
(3) 工程规模及功能分区:总建筑面积为6145m2,层数为六层,房屋高度为21.6m。各层使用功能如下:
一层∽二层:门面
三层∽六层:住宅
(4) 结构设计:基础为振动灌注桩基础、六层砖混、按七度抗震烈度设防,楼板除楼梯间、卫生间、厕所、客厅等为现浇板外,其余均为预应力空心板,砌体结构采用Mu10粘土砖、一至三层为M10混合砂浆、四至五层为M7.5混合砂浆、六层以上为M5混合砂浆,砼结构强度等级情况如下:
基础采用C20砼
现浇柱、梁、板除一至三层采用C30砼外,以上均为C20砼
现浇构造柱、圈梁采用C20砼
钢筋级别为Ⅰ、Ⅱ级。
(5) 屋面防水:刚性防水
(6) 建筑装饰
外墙:采用外墙漆
室内地面为水泥砂浆、内墙为混合砂浆。
1.2 施工部署
1.2.1 施工管理目标
为树立企业形象,实现各项管理目标,推行项目法管理,采用先进技术,精心组织、精心操作、优质、安全、高速、低耗建好该工程,具体目标如下:
工程质量:确保省优良工程。
施工工期:确保160天竣工交付使用。
安全生产:杜绝重大伤亡、设备、火灾事故。
文明施工:执行现场标准化管理,成为文明典范。
服务目标:与各方密切配合,为设备安装、装修施工创造条件,使业主满意。
1.2.2 施工组织管理机构设置
公司组建本工程项目经理部,代表公司具体对整个工程
A construction program
1.1 Project Overview
(1) Project Name: XX Township People's Government Complex Building
(2) Project Location: XX village people's government hospital
(3) The size of the project and functional area: The total construction area of 6145m2, was six storeys, housing a height of 21.6m. Layers using the following functions:
Two-story floor ∽: facade
Three ∽ six: Residential
(4) Structural design: base vibration of pile foundation, six-story brick, seven degree of seismic intensity according to fortification, except floor stairwell, bathroom, toilet, living room and so on board for the cast, the rest are prestressed hollow, clay brick masonry structure with Mu10, one to three for the M10 mixed mortar, mixing mortar four to five for the M7.5, six more than the M5 mixed mortar, concrete strength grade structure is as follows:
Using C20 concrete foundation
Cast columns, beams, plates with the exception of one to three C30 concrete, the above are concrete C20
Situ structural columns, ring beams and concrete use of C20
Steel grade for the grade Ⅰ, Ⅱ.
(5) Roofing: rigid waterproof
(6) Architectural Decoration
Wall: The outer wall paint
Indoor surface for the cement mortar, mixing mortar for the walls.
1.2 Construction of the deployment
1.2.1 Construction management objectives
To establish a corporate image, the achievement of management objectives, the implementation of the project management method, the use of advanced technology and careful organization and operation, high quality, safe, high-speed, low power built the project, specific objectives are as follows:
Quality of the project: to ensure that provincial excellent project.
Construction period: 160 days to ensure completion of delivery.
Safety: to prevent heavy casualties, equipment, and fire incidents.
Construction of civilization: the implementation of standardized management site, become a model of civilization.
Target: close cooperation with all parties for equipment installation, decoration works to create conditions for the satisfaction of the Owner.
1.2.2 Construction Management organization set
Incorporation of the Project Management Team, specifically on behalf of the company throughout the project
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次