北京世纪春天花园小区11、12、15、16楼临时用水、电施工.doc
1、编制依据
1.1北京世纪春天施工总平面图(2002-0806-06)
1.2《施工现场临时用电安全技术规范》(JGJ46-88)
1.3《北京市建筑工程施工安全操作规程》(DBJ01-62-2002 )
1.4《环境与职业健康安全手册》(CSCEC105-SC-02)
2、工程概况
北京世纪春天花园小区11、12、15、16#楼,位于北京市朝阳区望京新城,由北京世纪春天房地产开发公司投资建设,北京中天元设计有限责任公司设计,中环监理公司监理。
根据施工现场用电情况和用电设备的数量经与甲方协商,11、12#楼由一期低压配电室引来,15、16号楼由二期新建变压器室的低压配电柜引来。。由于变压器的位置与用电设备距离较远,施工设备比较分散,供电线路采用沿墙架设和地埋,同时施工现场的地理位置远离市区,周围无其他外线,地下没有外部电缆,因此安全距离符合规范要求。
施工现场配电室设2个A级配电箱,一个由一期变压器直接供电,另一个由二期变压器供电:AP-1供11、12#楼塔吊、砼泵、钢筋加工厂、木工车间等;AP-2供15、16号楼塔吊、砼泵、钢筋加工厂、木工车间、工人宿舍等用。
3、临电设计说明
3.1初步设计
由变压器直接供电给施工现场配电室,施工现场用电设备实行三级配电两级保护。根据施工现场临时用电“安全技术规范JG46-88”供电方式符合规范要求。
供电系统采用三相五线制TN-S供电系统,即工作零线N和
1, prepared according to
1.1 Beijing Century Spring Construction Map (2002-0806-06)
1.2 "Construction Site Temporary Electrical Safety Specifications" (JGJ46-88)
1.3 "Beijing Building Construction Safety Operation" (DBJ01-62-2002)
1.4 "Environmental and Occupational Health and Safety Manual" (CSCEC105-SC-02)
2, Project Overview
Beijing Century Spring Garden District 11,12,15,16 # Building, located in Chaoyang District, New Town, by the spring of Beijing Century Real Estate Development companies to invest in building design of Beijing Tianyuan Co., Ltd design, supervision of the Central Project Management Company.
According to the construction site electricity consumption and the amount of electrical equipment in consultation with the Party, 11,12 # floor from the room drew a low-voltage distribution, 15,16 the new building by the two low-voltage distribution transformer room cabinet cited years. . The transformer location and distance electrical equipment, construction equipment more decentralized, power transmission lines along the wall erected and buried, while the construction site's location away from urban areas, around no other outside, no external cables underground, so with the required safety distance.
Construction Site Power Distribution Room located two A-distribution box, a direct power supply from the one transformer, and the other by the two transformers supply: AP-1 for the 11,12 # floor tower crane, concrete pump, steel processing plants, carpentry shop, etc.; AP-2 for 15,16 Building tower crane, concrete pump, steel processing plant, a carpentry workshop, workers quarters use.
3, temporary electrical design specifications
3.1 Preliminary Design
Direct power supply from the transformer to the construction site power distribution room, electrical equipment on site to protect a three-level power distribution levels. According to the construction site of the temporary use of electricity "security specification JG46-88" power supply to meet the specification.
Power supply system using three-phase five-wire TN-S power supply system, that is, N and the zero line of work
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次