淀粉车间设备基础施工方案.doc
设备基础施工方案
一、工程概况:
淀粉车间工程设备较多,施工工艺复杂。 6月25日接到C、D区设备基础图纸(白图)。大块式设备基础底部采用C20毛石砼,SJ19.01—1,2、SJ20.01—3.4.5.6、SJ18.01—1.2填夯实,下部采用三、七灰土回填,三、七灰土范围为设备基础外边缘1500mm.由于C、D区的独立基础土方在6月23日已开挖完成。在整个土方开挖方案中由于不知道设备基础的底标高,无法一次性开挖,独立基础只有采用点式开挖方案,而对于设备基础土方只有采用二次开挖。现设备基础图有部分图纸已经下来(白图),图纸说明要求,“设备基础须设备到货经核对无误后方可施工”,为提前施工工期,争得业主同意,按目前白图施工,特制定本方案。
二、总体施工部署:
按设备基础下的结构设计,土方开挖分为两个区域,第一区域开挖有毛石基础部分,第二区域为开挖有三、七灰土
Equipment foundation program
1, Project Overview:
Starch plant engineering equipment more complicated construction process. June 25 received a C, D District equipment based on drawings (white figure). Massive use of equipment based on the bottom of the C20 rubble concrete, SJ19.01-1, 2, SJ20.01-3.4.5.6, SJ18.01-1.2 fill compaction, the lower part of a three, seven dust-filling, three, seven dust range equipment based on the outer edge of 1500mm. As the C, D District, the independent foundation in June 23 Earthwork excavation has been completed. Programs throughout the earth excavation equipment because they do not know the basis of the bottom elevation, not a one-time excavation, independent foundation excavation program only by point, but only used for the equipment based on the second excavation earthwork. Some devices are based on graph drawing has been down (white diagram), request the drawing, "device to device based on the arrival verified, before construction" for the early construction period, gain the consent of the owners, according to the current white drawings, special development of the program.
Second, the overall construction of the deployment:
Basis according to the structural design of equipment, soil excavation is divided into two regions, the first region based on some of rock excavation and hairy, and the second area for the excavation of three, seven dust
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次