小区半地下车库工程地下防水工程施工方案.doc
小区工程,包括4栋6.5+1层住宅楼和一个半地下车库,车库为钢筋混凝土框架结构,基础为独立基础,根据工程地质勘察报告得知,场地地下水位埋深为自然地坪以下0.5 M,该处地下水位埋深较浅。
车库工程基础施工过程中采取井点降水措施,昼夜不停降水,保证将地下水位控制在基础垫层以下50 CM。保证基础分部各工序施工过程中基槽干燥。
Community projects, including four 6.5 + 1 and a half storey residential building and underground garage, garage for the reinforced concrete frame structure, based on an independent basis, according to engineering geological investigation report that the venue for the natural groundwater depth floor the following 0.5 M , where shallow groundwater depth.
Garage foundation construction process to take well point dewatering measures precipitation around the clock to ensure that the water table based on the following Cushion 50 CM. Ensure that the process of construction is the basis of division over Chengzhong Ji slot drying.