悬挑卸料平台搭设方案及计算
根据本工程施工特征以及立面的情况和周边环境及满足周转材料的要求进行布置受料平台,以便将无法用人货电梯运输的材料,利用塔吊吊运到指定地点。
一、卸料平台的布置
根据现场施工情况,标准层以上每层设置一只,上下层错开布置,以便垂直吊运方便。
1、 D1幢:布置在M轴的SM3、J轴的SM2位置上,错开设置。
2、 D2幢:布置在A轴交4~8轴之间、1-K轴交1-6~1-8轴,错开设置。
3、 D3幢:布置在1-A轴交1-3~1-6轴、A轴交6~10轴,错开设置。
二、卸料平台的尺寸及组成
1、卸料平台的实际使用尺寸为2500×3500。(见附图
Cantilever erection scheme and the calculation of discharge platform
According to the construction features and the elevation of the situation and surrounding environment and to meet working capital requirements of the material furnished by the material platform, so that employers can not lift the transport of material goods, use of tower crane was being lifted to the specified location.
First, the arrangement of discharge platform
According to the site of the construction of each floor above the standard level 1, the lower staggered arrangement in order to facilitate vertical lifting.
1, D1 blocks: layout of the M axis of SM3, J SM2 axis position, staggered set.
2, D2 buildings: cross-axis arrangement in the A 4 to 8 axis ,1-K 1-6 ~ 1-8 axis cross-axis, staggered set.
3, D3 blocks: layout of the 1-A 1-3 ~ 1-6 axis cross-axis, A axis pay 6 to 10 axes, staggered set.
Second, the size and composition of the discharge platform
1, discharge platform, the actual use of size 2500 × 3500. (See photos
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次