一期工程办公楼屋面工程施工方案.doc
本工程屋面采用珍珠岩保温,SBS防水卷材结合防水涂膜聚氨酯防水层。
一、施工程序:
基层清理→管道堵洞、找平层→涂膜防水层→弹线→找坡层→保温层铺设→找平层→卷材防水层→面层。
施工要点:
1:8水泥珍珠岩找坡:找坡坡度为2%,操作前应在女儿墙上弹出标明珍珠岩铺设的厚度及坡度,另外,在屋顶做出找坡灰饼,以示珍珠岩铺设的厚度及坡度。铺设由高向低,最低处不得低于40mm。找坡层施工完毕,铺设100厚水泥珍珠岩保温块。
二、 卷材防水卷材施工
1、材料及要求:
防水卷材材料应具有出厂合格证或厂家产品的认证文件,材料进场后做复试,合格后方可使用。
2、主要机具:汽油喷灯、搅拌桶、滚刷、剪刀、压滚、清理工具等。
3、作业条件:
(1)基层应按设计要求抹好找平层,要求抹平、压光、坚实平整、不起砂,不空鼓,坡度符合设计,无积水现象。
(2)基层应基本干燥,含水率低于8%。
This works with perlite roof insulation, SBS waterproofing membrane combined with waterproof polyurethane waterproofing coating.
First, the construction process:
→ pipe plug hole grassroots clean-up, leveling layer of waterproof coating layer → → → elastic line to find slope laying insulation layer → → → leveling layer of waterproof layer → membrane surface.
Construction Highlights:
1:8 cement perlite to find slope: find slope gradient of 2%, operating before the wall in her pop-up marked the laying of the thickness and slope of perlite, also made in the roof slope to find ash cake, to show the laying of perlite thickness and slope. Laying from high to low, the lowest point not less than 40mm. Find slope layer construction is completed, the laying of 100 thick concrete perlite insulation block.
Second, membrane waterproofing membrane construction
1, material and requirements:
Waterproofing membrane material should have the factory certificate or certification of products from documents and materials to do re-testing after admission, qualified before use.
2, the main equipment: gas burner, stirring drum, roller brush, scissors, pressure roller, cleaning tools.
3, the operating conditions:
(1) primary design requirements should be smeared with leveling layer, required disappearing, the pressure of light, solid formation, can not afford to sand, not void, slope consistent with the design, no water phenomenon.
(2) basic primary should be dry, moisture content below 8%.
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次