中央音乐学院附中迁建工程卸料平台施工方案.doc
中央音乐学院附中迁建工程
卸料平台施工方案
审核:
审定:
编制:
一九九九年十二月二十四日
一. 工程概况
中央音乐学院附中迁建工程综合楼A区,地下一层,地上十六层。周转料投入为四层,为保证工程周转料的顺利使用,在主楼设一卸料平台,以满足工程施工的需要。
二. 卸料平台的制作和使用
卸料平台采用16#槽钢制作,宽度为2.5米,长度为6.5米,上铺5CM厚的木板,采用17的钢丝绳拉锚,于结构相连处采取在结构顶板上予留100*100洞,采用钢丝绳扣与之相连。具体的平台制作和安装见后附图
High School reconstruction project of the Central Conservatory of Music
Unloading platform construction plan
Audit:
Validation:
Prepared by:
December 24, 1999
1. Project Overview
Central Conservatory Complex Building A relocation project area, basement, ground floor 16. Material inputs for the four working, working material to assure the smooth use of a discharge platform located in the main building to meet the construction needs.
2. Unloading platform of the production and use of
Unloading platform, a 16 # channel steel production, a width of 2.5 meters, 6.5 meters in length, capped 5CM thick wood, with 17 of the wire rope anchor, connected with the structure we adopted in the roof on the structure to stay in 100 * 100 holes, connected by rope buckle. Production and installation of concrete platforms see below photos
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次