主楼升降机施工方案
编号: ZJWJ/QEO-AHDW-SGFA-017
1、升降机选型
本工程施工人员和小型材料的垂直运输主要通过升降机完成,考虑主楼施工层数和各楼层的工程量,拟采用型号为SCD200×200K,高度120m的升降机,安装在主楼西面。
2、升降机定位
升降机安装在地下室顶板上,位置确定在2~3交1/0A~A轴之间。机身与外架距离为20,附墙杆与A轴线框架梁预埋件连接,附墙杆安装高度分别为11、19.55、27.85、35.75、43.65、51.55、59.45、67.35、75.45、83.8、92.4、99.2米标高位置.
3、升降机基础
基础平面尺寸为6m×4m,板厚为h=400mm,配筋Φ10@200,双层双向,混凝土强度C30。具体做法如下图。
Main building lifts construction plan
ID: ZJWJ/QEO-AHDW-SGFA-017
1, lift selection
The construction and the vertical transport of small materials, mainly through the completion of the lift, consider the construction of floors and each floor of the main building of the project amount, to be adopted model SCD200 × 200K, height 120m lift, installed in the main building of the west.
2, lift positioning
Lift installed in the basement roof, the location identified in 2 or 3 axis AC 1/0A ~ A. Body and the outer frame distance of 20, with a wall rod and frame beam axis A link embedded parts, with a wall pole mounting height were 11,19.55,27.85,35.75,43.65,51.55,59.45,67.35,75.45,83.8,92.4 , 99.2 m elevation location.
3, lift foundation
Base plane size 6m × 4m, thickness is h = 400mm, reinforcement Φ10 @ 200, double two-way, concrete strength C30. Specifically, as shown below.
2009-8/主楼升降机施工方案.rar
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次