华 锐 世 界 广 场 一 期 工 程
地下室后浇带封挡施工方案
为保证华锐世界广场一期工程在冬期施工前能够提前进行地下结构工程的封挡围护,并确保地下室外防水和回填土工程的顺利进行,初步拟定在10月中下旬在本工程的地下部分结构完工后,对地下室的外墙后浇带进行封挡,特制定本施工方案。
主要施工方法:
一、地下室外墙后浇带的封挡
1.地下室外墙后浇带的封挡采用120厚600×1300mm C30混凝土预制板,由基础底板开始依次向上排放,上部两块预制板尺寸以现场实测实量尺寸为准。
Hua Rui world wide market a project
After pouring the basement construction plan block shot
To ensure Huarui Shi industry Plaza project in the winter before the construction is ahead of the block shot underground structural envelope, and that Outside waterproofing the basement and backfill progress of the works, tentatively in mid to late 10's underground in the works part of the structure after the completion of the basement wall to block shot after the pouring, construction plan is formulated.
The main construction methods:
First, the basement wall of the block shot after pouring
1. Basement wall block shot after the pouring of the 120 thick 600 × 1300mm C30 concrete precast panels, followed by the start up emissions of the base, the upper two panels size to actual measurements of the field test subject.
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次