双排脚手架计算书.doc
脚手架计算书
1、计算依据
(1)《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2001)
(2)《建筑结构荷载规范》(GB50009-2001)
(3)工程设计图纸及地质资料等
2、脚手架的计算参数
搭设高度H=39.6米(取最大高度,22排),步距h=1.8米,立杆纵距la=1.5米,立杆横距lb=1.1米,连墙件为2步3跨设置,脚手板为毛竹片,按同时铺设7排计算,同时作业层
Scaffolding calculations
1, calculated on the basis
(1) "construction steel tubular scaffold safety technical specifications" (JGJ130-2001)
(2) "Structural Load Standard" (GB50009-2001)
(3) engineering design drawings and geological data
2, the calculation of parameters of scaffolding
Erection height H = 39.6 m (maximum height taken, 22 rows), step away from h = 1.8 m vertical pole from the la = 1.5 m, horizontal pole from lb = 1.1 m, with wall pieces for the 2-step 3, cross-setting Scaffold board for the bamboo pieces, calculated according to the same time laying seven rows, while operating level
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次