工具式卸料平台施工方案.doc
工具式卸料平台施工方案
一、编制依据
1、《建筑施工高处作业安全技术规范》
2、《建筑施工手册》
3、《现行建筑材料规范大全》
二、卸料平台用途及极限荷载值
卸料平台是楼层进出材料的主要通道,主要用于输出拆下的模板和架管。为保证卸料平台的安全可靠及正常使用,卸料平台允许负荷的施工荷载不大于3000N/m2,最大负载为3600Kg,堆放高度不大于1米。
三、卸料平台的设计
1、平台形式
卸料平台为组装式,平台的主梁采用18
Tools unloader platform construction plan
1, prepared on the basis
1, "Construction work at heights safety technical specifications"
2, "Construction Manual"
3, "the current standard building materials Filmography"
2, unloading platform use and ultimate load values
Unloading platform is the floor of the main channel and out of materials, mainly for export templates and frame tube removed. To ensure safe and reliable unloading platform and normal use, loading unloading platform allows the construction of load is not greater than 3000N/m2, the maximum load 3600Kg, stacking height of not more than 1 meter.
Third, discharge Platform
1, the platform forms
Unloading platform assembled, the platform's main beam by 18
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次