某工程外墙外保温施工方案.doc
某工程外墙外保温施工方案
某工程外墙采用聚苯板抹灰外墙外保温方法施工,根据现场的实际情
况特制定如下施工方案。
(一)、施工条件
1、施工现场应作到通电、通水,并保持环境的清洁。
2、外墙和外门窗口施工及验收完毕。
3、操作地点环境温度和基层墙体表面温度均不得低于4℃,风力不大
Exterior Insulation Construction of a project plan
Polystyrene board used in a project wall Exterior Insulation construction method, according to the actual site conditions
State construction plan is formulated as follows.
(A), construction conditions
1, the construction site should be conducted with electricity, water, and keep the environment clean.
2, external wall and the outer door window construction and acceptance is completed.
3, the operation temperature and the primary place of wall surface temperatures are not lower than 4 ℃, little wind