幕墙工程作业指导书.doc
作业指导书
作业工序:施工前准备 作业工序号:NO—01
一.说明
工程项目经理要求对工程的工期进度、技术资料、工具、器具、材料、人员、机械、临时设施做好充分的准备。
二.施工前准备的内容范围
1.工程概况:对工地概况进行了解掌握,熟悉有
Operating Instructions
Operating procedures: preparation work before construction work number: NO-01
1. Explain
Project Manager required duration of the project progress, technical information, tools, equipment, materials, personnel, machinery, temporary facilities, fully prepared.
2. Preparing for the contents of the scope of construction
1. Project Overview: To understand the profile of the site are familiar with