一、工程概况
    本工程为唐山市宏扬花园商住楼工程,位于唐山市火炬路西侧,由唐山宏扬房地产开发公司招标筹建,唐山国旺建筑安装有限公司中标承建。工期为333天,要求2001年10月10日开工,2002年10月30日竣工交付使用。该工程由唐山市规划建筑设计研究院设计,建筑平面为5单元组合条式住宅楼。建筑面积为16757.66M2(其中地下室面积2310M2)。地下是一层半地下室,地上主体为六层。地下室层高2.2M,首层层高为3.6M,二层层高为3.0M,三至六层层高为2.9M,单元组合为一梯两户,一二层为商业用房,三至六层为住宅。该工程为框架结构。方案编制依据QTG250塔式起重机说明书、《塔式起重机安全规程》GB5144-94、《塔式起重机操作使用规程》JBJ80012-89、《建筑施工安全检查标准》(JGJ59-99)、《河北省〈建筑施工安全检查标准〉实施细则》等关于施工机具技术规范标准。
二、拆卸人员的组成和职责
1、拆卸人员主要由起重指挥(信号工)、起重工、拆卸工、电工等组成。原机操作人员和辅助拆卸的起重工,运输汽车的驾驶员为配合人员,还要配备机械或电气技术人员,由专业队
First, project survey
    To carry forward this project in Tangshan City Garden composite construction, is located in Tangshan City, torch Road west, real estate development company from the Tangshan Hong Yang, tender preparation, construction and installation, Ltd. Tangshan Guo wang bid construction. Duration of 333 days, requested October 10, 2001 started on Oct. 30, 2002 completion of delivery. The project by the Tangshan City Planning and Design Institute of Design, Architecture flat strip combination for the 5 unit residential building. Construction area 16757.66M2 (including basement area of 2310M2). Ground is a layer of semi-basement, main floor for the six. Basement storey 2.2M, first floor storey to 3.6M, two-story story is 3.0M, three to six layers high as 2.9M, unit mix is a ladder two and one two-story commercial buildings, three to six-storey residential. The project for the frame structure. Programming instructions according to QTG250 tower cranes, "tower crane safety regulations" GB5144-94, "tower crane operator using the order" JBJ80012-89, "construction safety inspection standards" (JGJ59-99), "Hebei Province," Architectural construction safety inspection standards for> the implementation details "and other technical specifications on the standards of construction equipment.
Second, the composition and responsibilities of the demolition workers
1, demolition workers mainly by lifting the command (signal work), lifting workers, demolition workers, electricians and other components. Former operator of a demolition crane and auxiliary workers, transport vehicles with driver for the staff, but also equipped with mechanical or electrical technicians, professional team
 

帮助中心 收藏 >>>
塔吊拆除方案示例1下载
点击此处下载