一、编制依据
龙门架及井字架物料提升机安全技术规范JGJ88-92,建筑施工扣件式钢管脚手架安全技术规范JGJB-2001,SBA150型开门自锁断绳保护自升门式提升架安装使用说明书。《建筑施工安全检查标准》JGJ59-99河北省建筑施工安全检查标准实施细则。
二、工程概况及安装条件
本工程为唐山市宏扬花园商住楼工程,位于唐山市火炬路西侧,由唐山宏扬房地产开发公司招标筹建,唐山国旺建筑安装有限公司中标承建。工期为333天,要求2001年10月10日开工,2002年10月30日竣工交付使用。该工程由唐山市规划建筑设计研究院设计,
1, prepared on the basis
Gantry and crosswise frame material hoist safety specifications JGJ88-92, construction steel tubular scaffold safety specifications JGJB-2001, SBA150-type self-locking door protection jack off rope elevator door frame installation instructions. "Construction safety inspection standards" JGJ59-99 Hebei Province, construction safety inspection standards implementation details.
Second, engineering survey and installation conditions
To carry forward this project in Tangshan City Garden composite construction, is located in Tangshan City, torch Road west, real estate development company from the Tangshan Hong Yang, tender preparation, construction and installation, Ltd. Tangshan Guo wang bid construction. Duration of 333 days, requested October 10, 2001 started on Oct. 30, 2002 completion of delivery. The project by the Tangshan City Planning and Design Institute of Design,
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次