临时用水、电、气管线及消防通讯设施的布置 第 1 页 共 1 页
   
    4.5临时用水、电、气管线及消防通讯设施的布置
    一、根据招标文件,业主提供管径为100的施工用水接头。施工、消防用水共用一个系统,并设计量装置,沿施工道路边布置。在每个建筑物处留有接口,现场设2只室外消防栓。干管为φ100钢管。
    二、建筑物室内配备适当数量的移动式消防灭火器材。
    三、在临时道路两边设置排水明沟,将场地雨水汇集,通过潜水泵提升排出场外。
    四、施工用电已由业主从外网接入厂区内。现场敷设电缆送到施工现场配电柜上、后根据施工需要分流到配电箱上。
    五、施工用氧气、乙炔、氩气等采用市场上供应的瓶装气,施工用压缩空气利用移动式空压机提供。
    六、施工现场设置8门电话分支,并与xx_分公司现有电话网相连。

主要建构筑物施工 第 1 页 共 1 页

主要形象进度 第 1 页 共 1 页

    5.1主要形象进度
    一、淡水厂工程拟定从xx月xx日_场开始施工,交工时间
Temporary water, electricity, gas pipelines and fire communications facilities layout Page 1 of 1 page
    
    4.5 temporary water, electricity, gas pipelines and fire communications facilities layout
    1, according to tender documents, owners of the construction of 100 diameter water connection. Construction, a fire water sharing system and designed measuring device, along the side of the road construction layout. Left in each building office interface, the scene set two outdoor fire hydrant. Trunk pipe for the φ100.
    Second, the building interior with an appropriate number of mobile fire fighting equipment.
    Third, set up temporary road on both sides of the drainage ditch, the site rainwater collection, through the submersible pump to enhance off-site discharge.
    4, construction electricity network from outside access by the owners of factories in the region. On-site laying cable distribution cabinet to the construction site, then under construction on the need to divert to the distribution box.
    5, construction with oxygen, acetylene, argon, etc. supplied by bottled gas market, the construction used with compressed air to provide mobile air compressor.
    6, the construction site set up eight telephone branch, and the existing telephone network with xx_ branch connected.

Construction of the main building structure 1 of 1 page

The progress of a main image of a

    5.1 The progress of the main image
    1, prepared from fresh plant projects _ field day xx xx months to start construction, the time for Completion
 