您现在的位置:主页 > 建筑工程 > 施工方案 > >>

后浇带施工方案.doc

资料评价:
★★★☆☆
更新时间:
2010-07-05
下载要求:
注册会员
文档大小:
0.08 MB
授权方式:
共享资料
上传会员:
lajks
文档类型:
.doc
所属栏目:
施工方案
需要金币:
1
资料语言:
简体中文
公告:免费注册 会员可立即获得金币,更多赚取金币方法请查看:金币说明 下载地址
资料简介:

  后浇带施工方案
 
在建筑工程中,通过设置后浇带来解决设计中考虑沉降差异或钢筋混凝土的收缩变形以及混凝土的温度应力等问题已广泛应用。后浇带施工是保证结构有效连接的重要环节。我司在施工石狮服装批发城(一期)工程中,重视后浇带各工序的施工质量,确保后浇带满足设计意图,从而起到它应有的作用。
    石狮服装批发城(一期)工程为地下1层、地上4层的框剪结构,其平面尺寸196m×66m。由纵向4道、横向1道1000mm宽后浇带将整个平面划分为10个施工段。后浇带长达460m。
1.后浇带的留设及支模
1.1  地下室底板、外墙后浇带
地下室后浇带施工中,底板、外墙后浇带防水是两个值得注意的问题。本工程地下水位-4.70~-4.50m,底板底标高为-4.60m,根据作业方案,人工挖孔桩施工阶段采用的深井降水措施,在垫层施工后停止。为防止地下水产生突涌,采用对底板后浇带处混凝土垫层施工进行加厚、提高混凝土强度等级,局部配筋等措施(见图1)。
Construction program after pouring
 
In construction work, poured through the set to bring the design to consider the settlement to resolve differences or reinforced concrete shrinkage strain and thermal stress of concrete problems have been widely used. Poured band structure of the construction is to ensure that an important part of effective connectivity. Our wholesale clothes in construction Shishi City (1) project, attach importance to the process after pouring construction quality, ensure that back strip to meet the design intent, to play its proper role.
    Shishi clothing wholesale City (1) works for the underground 1 floor, 4 floors of the wall structure, the plane size of 196m × 66m. 4 by the vertical and horizontal one 1000mm wide plane after pouring into the whole construction of section 10. After pouring over 460m.
1. The remained after the pouring and formwork
1.1 The basement floor, wall, after pouring
After pouring the basement construction, floor, wall poured with water are two notable problems. The project groundwater -4.70 ~-4.50m, the bottom floor elevation of-4.60m, according to work programs, manual digging deep pile used in the construction phase precipitation measures to cushion after construction stopped. To prevent ground water heaving on the floor with poured concrete liner construction with Department for thickening, increased concrete strength, reinforcement and other local measures (see Figure 1).
 

帮助中心 收藏 >>>
后浇带施工方案下载
点击此处下载