室外面砖粘贴施工技术交底.doc
一、施工准备
(一)作业条件
装修外用架子(高层多用吊篮或吊架)已经搭设好,并验收合格横竖杆及拉杆应离开墙面和窗口150—200mm,阳台栏杆、预留孔洞及排水管处理完毕,外门窗安装完毕,用1∶3水泥砂浆将缝隙堵塞严实,在外门窗为铝合金门窗及塑钢门窗时,为抢工期和成品保护,可以增做辅框,辅框采用镀锌方管,辅框内口边和窗侧旁贴完面砖平,窗比辅框上下、左右小5mm,以利于安装,辅框固定牢固,塞堵密实,并已经检验合格。如先安装完窗,要事先粘贴好保护膜,墙面基层清理干净,脚手眼、窗台、窗套等事先砌堵好,按面砖的尺寸、颜色进行选砖,并分类码放好。
大面积施工前应先放大样,并做出样板墙,确定施工工艺及操作要点,并向施工人员做好交底工作。样板墙完成后必须经质检部门鉴定合格后,还要经过设计、甲方、监理和施工单位共同认定,方可组织班组按照样板墙要求施工。
(二)材料要求First, construction preparation
(A) Operating conditions
Fitting external rack (top multi-purpose basket or hanger) has a good erection and acceptance anyway rod and bar, leave the wall and window 150-200mm, balcony railings, set aside, and drain holes disposed of, outer doors and windows installed, with 1:3 cement mortar to plug the gaps within sturdy, aluminum doors, windows and external doors and windows for the windows and doors, in order to grab the protection period and finished products can be done by secondary frame, auxiliary frame galvanized square tube, accessories and window frame mouth flat side next to the skin has tile, windows up and down than the auxiliary box, so small 5mm, to facilitate the installation of auxiliary frame fixed firmly, plug plug dense, and has been tested and qualified. Such as the first installation of windows, good protective film to advance paste, wall grassroots clean, Scaffold eyes, bay windows, window cover and other puzzle block well in advance, according to the size of tile, brick color selection and classification of laying is good.
Construction should be preceded by a large area to enlarge like, and make a model wall, construction technology and operations to determine the main points of clarification at work to do construction workers. Model after the completion of the wall must be accredited by the quality inspection department, the go through the design, Party, supervision and construction units together finds that the wall be a model organization requirements in accordance with the construction team.
(B) material requirements
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154873次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139022次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90906次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 屋面防水技术交底
- 1604次
- 建筑工程施工技术交底典型实录
- 1338次
- 工程施工安全技术交底资料库
- 761次
- 室内顶棚墙面粉刷技术交底
- 622次
- 室内消防管道及设备安装工艺技术交底
- 612次
- 挤密桩施工安全技术交底
- 596次
- 砖砌体工程技术交底
- 580次
- 室外面砖工程技术交底 外墙砖
- 571次
- 室内涂料及腻子施工技术交底
- 550次
- 火灾自动报警系统安装工艺技术交底记录
- 505次