一、施工准备
    (一)作业条件
    1、顶棚、墙面抹灰已完成,并已验收,屋面已做完防水层。墙面已弹好+50mm标高水平线。
    2、安装好门框并加防护,与地面有关的水、电管线已安装就位,穿过地面的管洞已堵严、堵实。
    3、做完地面垫层,按标高留出磨石层厚度(至少3mm)。
    4、石粒应分别过筛,并洗净无杂物。
    (二)材质要求

First, construction preparation
    (A) Operating conditions
    1, ceiling and wall plaster have been completed and acceptance, roof waterproofing has been done. Wall has a good +50 mm shells elevation level.
    2, installed door frame and add protection, and ground the water and electricity lines have been installed in place, through the surface of the tube holes are blocked Yan, blocking real.
    3, finished floor cushion, leaving a millstone by elevation of the thickness (at least 3mm).
    4, stone tablets should be separately sieved and washed debris-free.
    (B) material requirements