13人工成孔灌注桩工程.doc
一、 施工准备
(一) 作业条件
1、 人工成孔桩孔,井壁支护要根据该地区的土质特点、地下水分布情况,编制切实可行的施工方案,迸行井壁支护的计算和设计。
2、 开挖前场地完成三通一平。地上、地下的电缆、管线、旧建筑物、设备基础等障碍物均已排除处理完毕。各项临时设施,如照明、动力、通风、安全设施准备就绪。
3、 熟悉施工图纸及场地的地下土质、水文地质资料,做到心中有数。
4、 按基础平面图,设置桩位轴线、定位点;桩孔四周洒灰线,测定高程水准点。放线工序完成后,办理验收手续。
5、 按设计要求分段做好钢筋笼。
6、 全面开挖之前,有选择地先挖两个试验桩孔,分析土质、水文等有关情况,以此修改原编施工方案。
7、 在地下水位比较高的区域,先降低地下水位至桩底以下0.5m左右。
8、 人工挖孔操作的安全至关重要,开挖前对施工人员进行全面的安全技术交底;操作前对吊具进行安全可靠的检查和试验,确保施工安全。
(二) 材料要求
1、 水泥:采用32.5级以上普通硅酸盐水泥
First, construction preparation
(A) Operating conditions
1, artificial into the pile hole, retaining wall according to the characteristics of the region's soil, water distribution, preparation of practical construction program, borehole into line calculation and design support.
2, before the excavation site to complete leveling. Ground, underground cables, pipes, old buildings, equipment and other obstructions have been excluded based processed. The temporary facilities, such as lighting, power, ventilation, safety equipment ready.
3, familiar with the construction drawings and site of the underground soil, hydrogeology information, be aware of.
4, according to foundation plan, set the pile-bit axes, positioning points; Piles gray line around the spill to determine the standard point of elevation. Actinomyces process is complete, go through inspection procedures.
5, according to design requirements sub good reinforcement cage.
6, prior to full excavation, selected first hole dug two test piles, analysis of soil, hydrology and other relevant information in order to modify the original code construction scheme.
7, in the relatively high water table areas, first reduce the water table to pile the following about 0.5m.
8, manual digging operation is of utmost importance, before excavation of the safety of construction workers to conduct a comprehensive classification of components; operation before the spreader for safe and reliable inspection and testing, to ensure construction safety.
(B) material requirements
1 cement: The more than ordinary portland cement 32.5
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154873次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139022次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90906次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 屋面防水技术交底
- 1604次
- 建筑工程施工技术交底典型实录
- 1338次
- 工程施工安全技术交底资料库
- 761次
- 室内顶棚墙面粉刷技术交底
- 622次
- 室内消防管道及设备安装工艺技术交底
- 612次
- 挤密桩施工安全技术交底
- 596次
- 砖砌体工程技术交底
- 580次
- 室外面砖工程技术交底 外墙砖
- 571次
- 室内涂料及腻子施工技术交底
- 550次
- 火灾自动报警系统安装工艺技术交底记录
- 505次