分项、分部、单位工程的质量验收表格填写要领.doc
一、 分项工程的质量验收
1、 检验批质量的验收
分项工程分成一个或若干个检验批来验收。检验批合格质量应符合下列规定:
主控项目和一般项目的质量经抽样检验收合格;
具有完整的施工操作依据、质量检查记录。
(1) 主控项目。主控项目的条文是必须达到的要求,是保证工程安全和使用功能的重要保证项目,是对安全、卫生、环境保护和公众利益起决定性作用的检验项目,是确定该检验批主要性能的。如果达不到规定的质量指标,降低要求应相当于降低工程项目的性能指标,应会严重影响工程的安全性能;如果提高要求应等于提高性能指标,应会增加工程造价。如混凝土、砂浆的强度等级是保证混凝土结构、砌体工程强度的重要性能,所以说是必须全部达到要求的。
主控项目包括的内容主要有:
① 重要材料、构件及配件、成品及半成品、设备性能及附件的材质、技术性等。检查出厂证明及试验数据。其技术数据、项目符合有关技术标准规定。
结构的强度、刚度和稳定性等检验数据、工程性能的检测。如管道的压力试验;风管的系统测定与调整;电气的
1, sub-project quality acceptance
1, the quality of the acceptance inspection lot
Sub-projects into one or more inspection lot for acceptance. Pass the quality inspection lot shall meet the following requirements:
Master project and the general quality of projects that pass the test by sampling;
With a complete basis for the construction operation, quality control records.
(1) master project. Master program provisions are requirements that must be met is to ensure the safety and engineering features of the important guarantee for the project to use is a safety, health, environmental protection and public interest tests play a decisive role in the project, is to determine the main properties of the inspection lot. If you can not reach the quality target and reduce the requirements should be equivalent to reducing the project performance indicators that should seriously affect the project's safety performance; if we raise the requirements to improve performance should be equal, should increase the project cost. Such as concrete, mortar is to ensure that concrete strength grade, masonry work of the important properties of strength, so that it is necessary to meet the requirement of.
Include the contents of the master are:
① important materials, components and accessories, finished and semi-finished products, equipment and accessories of the material properties, technical and so on. Certificate of inspection and test data. Its technical data, projects to meet the technical standard requirements.
Structural strength, stiffness and stability of laboratory data, and engineering performance testing. Such as pipeline pressure test; air duct system in the determination and adjustment; Electric
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 检验批质量验收记录全套
- 5713次
- 江苏全套土建资料表格(word版)
- 2459次
- 智能工程建筑验收规范全套表格
- 1961次
- 分项、分部、单位工程的质量验收表格填
- 1901次
- revit软件教学视频全集打包下载
- 1480次
- 建筑工程施工质量验收资料学习材料表格
- 1476次
- 广东省建筑工程施工质量竣工验收资料表
- 1430次
- 北京建筑安装工程资料管理规程填写标准
- 1315次
- 检验批质量验收记录表填写范例
- 1298次
- 建设工程竣工验收备案需提交材料目录2
- 1153次