钢丝网岩棉夹芯复合板(简称GY板)是一种新型的墙体体板材,具有保温隔热、轻质、高强、隔声、防火、抗震和节能等优良性能。它兼有木结构的灵活分隔性和混凝土结构的耐久性,尤其适用于各类框架结构和低层建筑的内、外墙及建筑物的屋面保温层等处。
为保证CY板正常发挥使用功能,必须从产品的生产和安装,抹灰工艺几个方面进行严格控制。首先,工程上所用的GY板必须经出厂检验合格。用在隔墙处的GY板可接长使用,而用于屋面板和楼板的则不需接长,板面平整度应、符合预制混凝土构件的检验标准,应防止装卸搬运导致GY板发生破损或弯曲变形。其次,GY板与原有墙体和梁、板、柱、楼面的连接应采用承剪器或钢筋,且承剪器的固定方法、位置和钢筋的直径、长度必须符合设计要求。制作GY板的水泥、外加剂、石子、砂、钢材等原料的质量必须符合相应的质量检验标准规定。
1、施工程序
放线 安装连接配件 安装板材并固定 板缝嵌补加强 阴阳角及门窗口补强 安装预埋件 安装各种管路线盒 检查校正 抹灰及养护 做表面饰面层。
2、安装方法
⑴在安装GY板的设计位置,放
Steel wire wool sandwiched panels installation and plastering
Steel wire wool sandwiched panels (referred to as GY board) is a new wall plate body with thermal insulation, light weight, high strength, sound insulation, fire, earthquake and energy and other fine performance. It combines the flexibility of wood separated and the durability of concrete structures, especially for various types of low-rise frame structure and internal and external walls and roof insulation of buildings and other places.
CY board to play to ensure the normal use of function, must be the production and installation of several aspects of plastering process strictly controlled. First, the project GY used on board must pass inspection by the factory. Department used in wall board can be accessed GY long use, and for the roof and the floor is not required then a long board flatness should be in line with pre-cast concrete elements of the test, should prevent the loading and unloading lead to plate breakage GY or bending. Secondly, GY plate and the original walls and beams, plates, columns, floor bearing shear connection should be used, or steel, and bearing a fixed method of cutting device, location and diameter of steel, length must meet the design requirements. GY board made of cement, admixtures, gravel, sand, steel and other raw materials must meet the corresponding requirements of quality inspection standards.
1, the construction process
Installation accessories Installation of Actinobacillus connecting plate and fixed angle slab joint embedding and strengthening the yin and yang, reinforced door window installation to install all kinds of pipe junction box embedded parts inspection and maintenance to do calibration plaster surface finish layer.
2, Installation
⑴ GY board design the installation location, place
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160504次
- Autocad2013 64位32位破解版附带注册机
- 148303次
- 天正建筑8.5破解版
- 144040次
- autocad2012 64位32位 破解版(附注册
- 137474次
- 天正建筑8.2破解版
- 123386次
- autocad2010免费下载(简体中文版)
- 97140次
- CAD2008注册机及使用说明
- 80806次
- 免费农村房屋设计图
- 73708次
- cad图集大全
- 56745次
- 11g101图集全套下载
- 45262次
- 总进度计划横道图及施工进度网络图--范
- 1228次
- 土木工程毕业设计论文(建筑类)
- 949次
- 钢筋翻样表格
- 769次
- 常用标准螺母规格及通径对照表
- 713次
- 3DMAX建筑模块
- 616次
- 施工员常用多面体的体积和表面积计算公
- 581次
- 工程常用物质的热物理性质手册
- 541次
- Autodesk_Revit_Architecture_2012_Win
- 509次
- 新水泥标准强度等级与老标准的水泥标号
- 490次
- 竣工图图框格式
- 443次