中国网通西南通信枢纽楼施工组织设计.doc
一、编制依据
(一)中国网通集团公司四川省分公司关于中国网通西南通信枢纽大楼的相关要求。
(二)中国建筑西南设计研究院的《中国网通西南通信枢纽大楼》工程施工图(设计号:06103-01)。
(三)成都市兴蜀勘察基础工程公司提供的场地详细勘察阶段岩土工程勘察报告书。
(四)国家现行的施工和验收规范、规程、标准和关于建筑施工管理等方面的技术文件、图集以及相关的法律法规。
(五)质量管理体系(依据GB/T19001-2000标准)。
环境管理体系(依据GB/T24001-1996标准)。
职业健康安全管理体系(依据GB/T28001-2001标准)。
二、编制说明
(一)在接到中国网通集团公司四川省分公司关于中国网通西南通信枢纽大楼的相关要求和设计图纸后,公司组织工程技术人员对该要求和图纸进行仔细认真的研究,反复阅看,召开了预备会,针对本工程的重、难点进行研究,方案论证对比,力求编制的施工组织设计科学、合理、详尽,具有很强的针对性和可操作性。
(二)在现场进行踏勘实测实量后,获得了宝贵的第一手数据,对场地、周边环境、地形地貌、围挡情况、施工供水排水供电情况,有了一定的了解,这对施工组织设计的制定起着重要作用。
(三)我公司经过多年的运作,积累了较为丰富的施工经验,形成了1, prepared on the basis
(1) China Netcom China Netcom Group Corporation Sichuan Province, southwest branch communications hub on the relevant building requirements.
(2) China Southwest Architectural Design and Research Institute's "communications hub of Southwest China Netcom Building" project construction drawings (design No. :06103-01).
(C) Revive Sichuan Chengdu survey based engineering company to provide detailed investigation stage of the site geotechnical investigation report.
(D) current national construction and acceptance of norms, rules, standards, and on construction management, technical documents, Atlas and the relevant laws and regulations.
(E) quality management system (based on GB/T19001-2000 standard).
Environmental management system (based on GB/T24001-1996 standard).
Occupational Health and Safety Management System (based on GB/T28001-2001 standard).
Second, the preparation instructions
(A) Upon receipt of Sichuan Province, China Netcom Group, China Netcom, Guan Yu Fen Gongsi communications hub building southwest of the relevant requirements and design drawings, the company's tissue engineering and technical personnel of such request and drawings carefully careful study, repeated access to view, held the preparation will, for the construction of heavy and difficult to study, the program demonstrated contrast, sought to prepare the construction organization design scientific, rational, detailed, highly relevant and practical.
(B) measured in the field survey and investigation, after the actual volume, gained valuable first-hand data on the site, surroundings, topography, Wei Dang case, construction drainage water supply situation, with some understanding, which construction organizations Design plays an important role in the formulation.
(C) the operation of our company over the years has accumulated more experience in construction, formed
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 建筑工程施工组织设计范本
- 5300次
- ***高层施工组织设计
- 1831次
- 免费高层建筑施工组织设计
- 1790次
- 小高层施工组织设计
- 1473次
- 新校区综合楼工程施工组织设计
- 1458次
- 住宅楼工程施工组织设计
- 1344次
- 一类高层建筑施工组织设计
- 1335次
- 科嘉花园小区6、8、14、16、17#楼施工
- 1291次
- 施工组织设计方案
- 972次
- 免费超高层建筑施工组织设计方案实例
- 962次