目 录
第一部分:编制依据-------------------------------------------5
1.编制依据-------------------------------------------------6
第二部分:工程概况-------------------------------------------9
2.1 工程基本情况-------------------------------------------10
2.2 工程关键项目-------------------------------------------21
2.3 工程施工流程 --------------------------------------------22
第三部分:施工部署------------------------------------------24
3.1 项目管理机构及职能(含职责划分)------------------------25
3.2 项目管理主要目标--------------------------------------28
3.3 施工准备----------------------------------------------29
3.4 施工平面布置------------------------------------------30
3.5 临时设施----------------------------------------------32
第四部分:主要施工机具和劳动力使用计划----------------------33
4.1主要施工机具计划--------------------------------------34
4.2劳动力计划--------------------------------------------37
第五部分:施工进度计划和保证措施 ---------------------------39
5.1施工进度计划控制--------------------------------------41
5.2 进度计划保证措施--------------------------------------43
5.3进度计划表--------------------------------------------44
第六部分:主要保证措施---------------------------------------45
6.1质量保证措施------------------------------------------46
6.2 安全保证措施------------------------------------------59
6.3 成品保护措施------------------------------------------66
6.4 文明施工管理措施--------------------------------------67
6.5 环保控制措施------------------------------------------68
6.6 “非典”预防措施----------------------------------------72
6.7 各方配合措施------------------------------------------78
6.8 服务保证措施------------------------------------------87
6.9 雨季施工措施------------------------------------------88
第七部分:主要分部分项工程施工措施--------------------------93
7.1土建工程-----------------------------------------------94
7.1.1 钢结构----------------------------------------------94
7.1.2 结构加固--------------------------------------------103
7.1.3 钢筋混凝土工程和室外工程----------------------------114
7.1.4 其它------------------------------------------------120
7.1.5 测量控制管理----------------------------------------121
7.2 空调工程----------------------------------------------127
7.3 电气工程----------------------------------------------134
7.4 给排水工程--------------------------------------------150
7.5 装修工程----------------------------------------------167
第八部分:施工技术管理--------------------------------------193
8.1计量管理-----------------------------------------------194
8.2 技术资料管理------------------------------------------194
8.3 图纸设计深化管理--------------------------------------195
附表:
1. 质量保证体系图
2. 安全保证体系图
3. 项目主要成员名单
4. 施工进度计划表
5. 施工现场平面图
6. 主要材料一览表
CONTENTS
Part I: preparation according ------------------------------------------- 5
1. Preparation according ---------------------------------------------- --- 6
Part II: Project Overview ------------------------------------------- 9
------------------------------------------- 2.1 Basic Engineering 10
2.2 Project Key ------------------------------------------- 21
-------------------------------------------- 22 2.3 Construction Process
Part III: Construction of the deployment ------------------------------------------ 24
3.1 Project management agencies and functions (including segregation of duties )------------------------ 25
3.2 The main objective of project management, -------------------------------------- 28
Construction preparation ---------------------------------------------- 29 3.3
------------------------------------------ 30 3.4 Construction layout
3.5 Temporary facilities ---------------------------------------------- 32
Part IV: Major construction machinery and labor use plan ---------------------- 33
4.1 The 34 key construction equipment plan --------------------------------------
-------------------------------------------- 37 4.2 Workforce Planning
Part V: The construction schedule and ensure that measures --------------------------- 39
5.1 Construction Schedule Control -------------------------------------- 41
5.2 schedule assurance measures -------------------------------------- 43
5.3 Progress Form -------------------------------------------- 44
Part VI: The main assurance measures --------------------------------------- 45
6.1 Quality assurance measures ------------------------------------------ 46
Safety assurance measures 6.2 ------------------------------------------ 59
6.3 product protection ------------------------------------------ 66
6.4 civilized construction management -------------------------------------- 67
------------------------------------------ 68 6.5 Environmental control measures
6.6 "SARS" prevention ---------------------------------------- 72
6.7 with the measures the parties ------------------------------------------ 78
------------------------------------------ 87 6.8 service assurance measures
6.9 Construction of measures in the rainy season ------------------------------------------ 88
Part VII: The main sub-part of the project construction measures -------------------------- 93
7.1 Civil Engineering ----------------------------------------------- 94
7.1.1 Steel --------------------------------------------- -94
7.1.2 Structural Strengthening -------------------------------------------- 10.3
7.1.3 Reinforced concrete works and external works ---------------------------- 114
7.1.4 Other ---------------------------------------------- - 120
7.1.5 Survey control ---------------------------------------- 121
7.2 The air conditioning works ---------------------------------------------- 127
7.3 Electrical Engineering ---------------------------------------------- 134
7.4 Water Supply and Drainage Project -------------------------------------------- 150
7.5 renovation ---------------------------------------------- 167
Part VIII: Construction Technology Management -------------------------------------- 19.3
8.1 Measurement and Management ----------------------------------------------- 194
8.2 Technical Data Management ------------------------------------------ 194
8.3 Drawing design development management -------------------------------------- 195
Schedule:
1. Quality assurance plan
2. Safety Assurance System Chart
3. Project a list of key
4. Construction progress schedule
5. The construction site plan
6. Main material list
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 建筑工程施工组织设计范本
- 5300次
- ***高层施工组织设计
- 1831次
- 免费高层建筑施工组织设计
- 1790次
- 小高层施工组织设计
- 1473次
- 新校区综合楼工程施工组织设计
- 1458次
- 住宅楼工程施工组织设计
- 1344次
- 一类高层建筑施工组织设计
- 1335次
- 科嘉花园小区6、8、14、16、17#楼施工
- 1291次
- 施工组织设计方案
- 972次
- 免费超高层建筑施工组织设计方案实例
- 962次