80米砼烟囱施工组织设计.doc
一、施工部署:
由于本工程工期相对较短,我单位安排一个专业施工队伍,负
责钢筋混凝土烟囱施工。由于本工程工种较多,工程量与劳动力的配
备不可能完全均衡,因此,台上、台下均采取专业、混合相结合的综
合劳动组织形式,强调分工协作。
1、工期安排
从基础挖土到混凝土浇筑、回填土完毕,计划用时105 天。其
中从±0 开始到筒身施工结束,计划用时60 天。First, the construction plans:
As the relatively short duration of this project, I arranged a professional construction team units, negative
Responsible for construction of reinforced concrete chimney. As more of this type of work projects, engineering capacity and the labor force with
Equipment can not be completely balanced, so the stage, the audience are a professional, mixed comprehensive combination
Co-work organization, stress division collaboration.
1, time arrangement
From the foundation excavation to concrete placement, backfill is completed, plans to use the time 105 days. Its
± 0 from the beginning to the end of Silo body construction, plans to use about 60 days.