临时用电施工组织设计

工程名称 八里店镇**标准厂房
四标段28#楼 工程地点 八里店镇**曹报村
建筑面积(M2) 11811.6 建筑高度(M) 14.2 开工日期 2005.8.25
施工现场勘测情况(现场的地形、地貌,正式工程的位置,建筑材料、器具堆放位置,生产、生活暂设建筑物位置,用电设备装设位置,现场周围环境等):
本工程落址于八里店镇**曹报村,东临空地,南临公寓、西临空地、北临27#楼。建筑物东西长108米,南北宽36米、结构层次三层,结构类型框架结构,平面呈长方形。施工现场建筑材料按平面布置图堆放。木工制作及模板堆放在建筑物中间的西北面,钢筋制作场及堆放在建筑物东北面;搅拌机、水泥罐、黄砂、碎石、砖堆放场等材料堆放在建筑北面。QTZ40T/M安装在建筑物北面。钢筋机械、电焊机、圆盘机等各机械摆放在钢筋、模板制作场地。生活设施:民工宿舍、食堂、男、女厕所、淋浴室暂时设置在施工现场外面的西面。传达室设置东北面,仓库、办公室设置在建筑物西北面,施工现场的总配电箱安装在建筑物西北面,1#、2#、3#、4#、5#、6#、7#动力分电箱和1#、2#、3#照明分配电箱,各箱安装在各机械设备旁。建筑物四周用砖围墙围护,进出主入口设置在东面,现场施工用电具体详见表四、表七、表十一、

Design of the temporary use of Electricity

Project Name Zhen ** standard factory Bali
4 Lot 28 # Building Project site reports Pali village Cao Zhen **
Floor area (M2) 11811.6 building height (M) 14.2 start date 2005.8.25
Surveying the construction site conditions (site topography, the official position of the project, building materials, appliances stacked position, production and life of temporary building location, location of electrical equipment installation, on-site environment, etc.):
This project off the site in the North reportedly Cao Zhen ** village, east of the open space, apartment south west open space, bounded by 27 # floor. Building 108 meters from east to west, north and south 36 meters wide, three-level structure, the structure type of frame structure, flat rectangular. The construction site of building materials stacked by floor plans. Wood production and templates stacked in the middle of the northwest building, steel production and the stacked field northeast of the building; mixer, cement tanks, yellow sand, gravel, bricks and other material stacked in storage field construction north. QTZ40T / M installed in the building north. Steel machinery, welding, machine and other mechanical disc placed in the steel, the template-production. Living facilities: migrant workers dormitories, canteens, men, ladies room, shower room being set up at the construction site outside of the west. Janitor's room set the northeast, warehouses, office buildings set in the northwest, the construction site of the main distribution box installed in the building north-west, 1 #, 2 #, 3 #, 4 #, 5 #, 6 #, 7 # Power Distribution box and 1 #, 2 #, 3 # lighting electrical distribution box, the box next to mechanical equipment installed in each. Brick wall around the building envelope, and out of the main entrances to the east, on-site Construction Power specific see Table 4, Table 7, Table 11,
 