一、工程概况
    本合同段土方路基段底基层是采用32CM厚的石灰粉煤灰碎石,分两层,每层16CM厚,计239480m2 。双幅主车道,各8米宽,中间由8米宽绿化分隔带分隔开。二灰碎石七天无侧限抗压强度为0.8MPa,压实度为98%。

二、施工准备
  1、人员准备:(见主要管理人员配备一览表)
  2、机械设备:(见机械设备配备一览表)
  3、材料准备:采用预拌商品混合料。
  4、测量准备工作:
(1)在基层边缘以外30cm处,纵向每隔10m,钉基准桩(直径12mm~15mm长600mm),铁桩一端制成尖头。
(2)在基准桩上用螺栓固定横梁,横梁亦为铁质(直径12mm~15mm长300mm),待测量高程后再紧固横梁,横梁必须呈水平状。 
(3)在基准桩横梁上架高直径3mm钢丝绳基准线,基准线钢丝绳放在横梁的刻梁槽内以免基准线在横梁上左右滑动。
(4)基准线顶面与铺筑的二灰碎石(砂砾)基层面的垂直距离为10~30cm。
(5)基准线两端用紧线器拉直绷紧,其拉力应不小于800N。
(6)施工过程中设专人对铁桩、基准线做好看护工作。
5、施工现场准备工作:
  (1)在准备施工二灰碎石基层前,验收底基层的高程、宽度、厚度、横坡、压实度等各项质量指标符合设计要求,表面平整坚实、无坑洼、松散、弹软现象。
 (2)对路面底基层进行清扫First, project survey
    Section of earth embankment section of this contract, sub-base is used 32CM thick lime fly ash gravel, sub-floors, each floor 16CM thickness, namely 239480m2. Double width main road, the 8-meter-wide, the middle of the 8-meter-wide green median separated. Seven days of lime unconfined compressive strength of 0.8MPa, 98% degree of compaction.

Second, construction preparation
  1 staff to prepare: (see key management personnel with a list of)
  2, machinery and equipment: (see list of machinery and equipment is equipped)
  3, material preparation: The ready-mixed product mixture.
  4, measuring the preparatory work:
(1) outside the edge of 30cm Department at the grassroots level, vertical intervals of 10m, nail base pile (diameter 12mm ~ 15mm length 600mm), iron pickets made one end pointed.
(2) in the base pile on bolted beam, the beam is also iron (diameter 12mm ~ 15mm length 300mm), then tighten the beam to be measured elevation, beams to the level was like.
(3) in the base pile beam diameter of 3mm wire shelves high baseline baseline rope on the beam beam slot carved in the beams on the baseline to avoid sliding around.
(4) baseline and paved top surface of lime (gravel) primary side of the vertical distance of 10 ~ 30cm.
(5) baseline at both ends of the thread with a tight straighten tight, the tension should be not less than 800N.
(6) set the course of construction hand on the iron pickets, good baseline care work.
5, construction site preparation work:
  (1) in preparation for construction of two gray gravel before the acceptance of sub-base of the height, width, thickness, cross slope, compaction and other quality indicators meet the design requirements, a solid flat surface, no potholes, loose, soft shells phenomenon.
 (2) of the road sub-base for cleaning