1江苏省高速公路工程石灰粉煤灰稳定土路面底基层施工指导意见.doc
路面底基层是在基层下铺筑的承重层,江苏高速公路路面,采用石灰、粉煤灰稳定土(简称二灰土)底基层,结构厚度20cm。
高速公路施工难度大、技术要求高,因而在路面施工中,必须层层把关,严格要求。从底基层应给予高度重视,防止在二灰土底基层施工中出现原材料质量不合格、配合比不准确、拌和不均匀、碾压不密实、接缝不平整等质量弊病,避免出现粘土夹层、起皮、松散、裂缝、弹簧、翻浆等质量缺陷,以确保路面底基层的工程质量。
根据交通部标准JTJ034-2000《公路路面基层施工技术规范》结合江苏已建成高速公路路面施工经验,对路面二灰土底基层施工,提出如下指导意见。
一、 准备工作
1、 必须配备齐全的施工机具和配件,做好开工前的保养、试机
工作,并保证在施工期间一般不发生有碍施工进度和质量的故障。底基层采用单幅路拌法一层摊铺施
r road sub-base under the pavement at the grassroots level of load-bearing layer, Jiangsu Expressway road, using lime, fly ash stabilized soil (referred to as lime and fly ash) sub-base, structural thickness of 20cm.
Highway construction difficult, technically demanding and therefore road construction, must be checks at each level, strict requirements. From the sub-base should be given high priority to prevent the sub-base construction in lime and inferior quality of raw materials appear to meet the ratio is not accurate, uniform mixing, rolling is not dense, uneven joints and other quality defects, to avoid the clay interlayer, since Paper, loose, cracks, springs, boiling and other defects, to ensure that the road sub-base of the project quality.
According to the Ministry of Communications standards JTJ034-2000 "Specification for Highway Pavement Base Construction" combined with Jiangsu Expressway road construction experience has been built on the road sub-base construction of the second lime, the following guidance.
First, preparatory work
1, must be equipped with a full range of construction machinery and accessories, do pre-construction maintenance, testing machine
Work, and to ensure that generally do not occur during the construction impede construction progress and quality of fault. Sub-base layer with single width road paving mix Method Shi
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160780次
- Autocad2013 64位32位破解版附带注册机
- 148385次
- 天正建筑8.5破解版
- 144084次
- autocad2012 64位32位 破解版(附注册
- 137477次
- 天正建筑8.2破解版
- 123424次
- autocad2010免费下载(简体中文版)
- 97157次
- CAD2008注册机及使用说明
- 80847次
- 免费农村房屋设计图
- 73852次
- cad图集大全
- 56934次
- 11g101图集全套下载
- 45655次
- 沉井施工方案
- 1654次
- 石方爆破施工方案
- 1531次
- 土方回填施工方案
- 1174次
- 水泥稳定级配碎石基层施工方案
- 983次
- 沉管灌注桩施工方案
- 919次
- 石拱桥工程施工方案
- 773次
- 路基排水工程施工方案
- 732次
- 珠江新城隧道施工方案
- 663次
- 给水管道、消防管道和排风管道安装工程
- 561次
- SPJ30-300型架桥机施工方案图(CAD)
- 525次