水泥稳定碎石层施工方案
一、工程概况
本合同段土方路基段基层是采用16CM厚的水泥稳定碎石层。双幅主车道,各8米宽,中间由8米宽绿化分隔带分隔开。水泥稳定碎石层七天无侧限抗压强度为3.5MPa,压实度为98%。
水泥稳定碎石层的一般要求:
(1) 城市道路的快速路和主干道的水泥稳定级配碎石混合料应采用厂拌法进行拌和。并用摊铺机摊铺混合料。
(2) 水泥稳定级配碎石做基层施工时水泥及混合料必须合格,粒料级配符合要求,配合比、混合料拌和均匀。铺筑后的高程、厚度、横坡、压实度各项质量指标符合规定要求。
(3) 水泥稳定级配碎石做基层时,水泥剂量不宜超过6%.压实厚度不应超过20cm。
(4) 在雨季施工水泥稳定级配碎石基层时,应特别注意气候变化,勿使水泥和混合料受雨淋。降雨时应立即停工,已经摊铺的水泥碎石混合应尽快碾压密实。并做好下承层的排水工作。
(5) 水泥稳定级配碎石基层宜在春末和气温较高季节组织施工。施工期的日最低气温应在50C以上,在有冰冻的地区,并应第1次冰冻(-3~-50C)到来之类前半个月到一个月完成。
(6) 施工中尽可能缩短拌和内加水拌和到碾压终了的延迟时间不应超过2小时。
(7) 洒水养生不宜少于7天基层表面始终保持湿润。
材料要求:
1. 水泥
(1) 普通硅酸盐水泥、矿渣硅酸盐水泥火山灰水泥都可以用于稳定级配碎石,但应选用初凝时间较长以及受潮变质水泥不应使用。宜用标号325水泥。
(2) 水泥应符合规定的技术标准。
2、碎石
(1)颗粒的最大粒径不应超过31.5mm,对所用
Construction of cement stabilized gravel layer program
First, project survey
Section of earth embankment section of this contract is used 16CM thick primary cement stabilized crushed stone layer. Double width main road, the 8-meter-wide, the middle of the 8-meter-wide green median separated. Seven days a cement stabilized gravel unconfined compressive strength of 3.5MPa, 98% degree of compaction.
Cement Stabilized Crushed Stone general requirements:
(1) Urban expressways and trunk roads of cement stabilized gravel mixture should be mixing plant mixing method. With paver mixture.
(2) made of cement stabilized gravel and grass-roots construction of the cement mixture to be qualified, aggregate gradation to meet the requirements, with the ratio, mixing mixture evenly. After paving the elevation, thickness, cross slope, degree of compaction of the quality indicators to meet the requirements.
(3) The cement stabilized gravel do grass-roots, the cement dosage should not exceed 6%. Compacted thickness should not exceed 20cm.
(4) in the rainy season the construction of cement stabilized macadam base should pay special attention to climate change, must not allow mixture of cement and by the rain. Rainfall should be immediately suspended and has been spreading the cement rolling as soon as possible compacting gravel mixed. And make the drainage work under the commitment level.
(5) cement stabilized macadam base should the higher temperatures in late spring and the season of construction. Construction of the daily minimum temperature should be 50C or more, in a frozen area, and should be 1st frozen (-3 ~-50C) to the arrival of the first half like a month to complete.
(6), shortened as much as possible the construction of mixing water within the compacted mixture to the end of the delay should not exceed 2 hours.
(7) sprinkler health should not be less than seven days the surface is always moist grass-roots level.
Material requirements:
1. Cement
(1) ordinary portland cement, pozzolanic cement slag cement can be used to stabilized gravel, but should use a longer initial setting time and moisture deterioration of cement should not be used. Cement grade 325 is preferred.
(2) Cement shall meet the required technical standards.
2, gravel
(1) the maximum particle size should not exceed 31.5mm, on the use of
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160780次
- Autocad2013 64位32位破解版附带注册机
- 148385次
- 天正建筑8.5破解版
- 144084次
- autocad2012 64位32位 破解版(附注册
- 137477次
- 天正建筑8.2破解版
- 123424次
- autocad2010免费下载(简体中文版)
- 97157次
- CAD2008注册机及使用说明
- 80847次
- 免费农村房屋设计图
- 73852次
- cad图集大全
- 56934次
- 11g101图集全套下载
- 45655次
- 沉井施工方案
- 1654次
- 石方爆破施工方案
- 1531次
- 土方回填施工方案
- 1174次
- 水泥稳定级配碎石基层施工方案
- 983次
- 沉管灌注桩施工方案
- 919次
- 石拱桥工程施工方案
- 773次
- 路基排水工程施工方案
- 732次
- 珠江新城隧道施工方案
- 663次
- 给水管道、消防管道和排风管道安装工程
- 561次
- SPJ30-300型架桥机施工方案图(CAD)
- 525次