土方工程作业指导书
一般规定:
土石方工程应合理选择施工方案,编制、审批、实施符合九九定额精神,尽量采用新技术和机械化施工。
施工中如发现有文物或古墓等应妥善保护,并应立即报请当地有关部门处理后,方可继续施工。
在敷设有地上或地下管道、光缆、电缆、电线的地段施工进行土方施工时,应事先取得管理部门的书面同意,施工时应采取措施,以防损坏。
土石方工程应在定位放线后,方可施工。
土方工程施工应进行土方平衡计算,按照土方运距最短、运程合理和各个工程项目的施工顺序做好调配,减少重复搬运。
1、场地平整
1.1、操作方法:
关键是测量,随干随测,最终测量作好书面记录。实地测点标识,作为检查、交验的依据。
填方应选用符合要求的土料,边坡施工应按填土压实标准进行水平分层回填压实。
平整场地后,表面逐点检查,检查点的间距不宜大于20M。
1.2.质量要求及标准:
Earthworks operation instructions
General provisions:
Earthwork construction plan should be a reasonable choice, preparation, approval, implementation of the spirit of the fixed line 99, to maximize the use of new technologies and mechanization in construction.
Construction as found in tombs and other relics or should be properly protected, and should be treated immediately report to local authorities, can continue the construction.
In laying there on the ground or underground pipes, cables, cable, wire construction for earthwork construction site, should obtain prior written consent of management, construction should take measures to prevent damage.
Earthwork should be put in the positioning line, before construction.
Construction of earthwork earthwork balance calculation should be carried out in accordance with the shortest distance earth, fortune and all reasonable construction of the Project in order make the deployment, reduce duplication removal.
1, site preparation
1.1, methods of operation:
The key is to measure, with the dry with the test, make a written record of the final measurement. Field measuring point identification, as inspection, the basis for examination.
Fill should be used to meet the requirements of the soil material, compacted fill slope construction standards should be the level of backfill compaction layer.
After leveling the ground surface, point by point inspection, checkpoint spacing not greater than 20M.
1.2. Quality and standards:
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160780次
- Autocad2013 64位32位破解版附带注册机
- 148385次
- 天正建筑8.5破解版
- 144084次
- autocad2012 64位32位 破解版(附注册
- 137477次
- 天正建筑8.2破解版
- 123424次
- autocad2010免费下载(简体中文版)
- 97157次
- CAD2008注册机及使用说明
- 80847次
- 免费农村房屋设计图
- 73852次
- cad图集大全
- 56934次
- 11g101图集全套下载
- 45655次
- 沉井施工方案
- 1654次
- 石方爆破施工方案
- 1531次
- 土方回填施工方案
- 1174次
- 水泥稳定级配碎石基层施工方案
- 983次
- 沉管灌注桩施工方案
- 919次
- 石拱桥工程施工方案
- 773次
- 路基排水工程施工方案
- 732次
- 珠江新城隧道施工方案
- 663次
- 给水管道、消防管道和排风管道安装工程
- 561次
- SPJ30-300型架桥机施工方案图(CAD)
- 525次