QX-ZY-2002-31
1、主题内容及适用范围  
本作业指导书对水利水电工程中土方碾压填筑的施工工艺进行了规范。适用于土坝,堤防等碾压土方填筑工程施工。
2、 引用标准
SDJ213-83   《碾压式土石坝施工技术规范》
SL260-98    《堤防工程施工规范》
SL38-92     《水利水电基本建设工程单元工程质量等级评定标准(七)》
SL239-1999  《堤防工程施工质量评定与验收规程》
3 、施工准备
3.1对合同及设计文件进行深入具体条件编好施工组织设计
3.2做好各项技术准备,并做好“四通一平”临建工程,各种设备和器材的准备工作。导流及引排水工程已完成。
3.3测量放样工作已验收合格,对主要测点已埋设牢固的标架、基石、坝(堤)身放样已按设计预留沉降量。
3.4对土料场进行现场核查,贮量应大于需用量的1.5-2.5倍。土质及天然含水量符合设计要求。
3.5施式机械、试验设备到位,已做防渗体土料碾压试验,基础清理已完成并经过验收。
4 、施工操作要求
4.1土料开挖
4.1.1料场开挖前应划定开挖范围,清除树根乱石及妨碍施
Hangzhou Hongsheng Consulting
Compacted earth embankment construction work instructions
QX-ZY-2002-31
1, the subject content and application
The work instructions on Water Resources and Hydropower Engineering Construction Earthwork Filling rolling process was standardized. Applied to dam, dike construction and other rolling earthwork.
2, reference standards
SDJ213-83 "rolled earth dam construction specification"
SL260-98 "Embankment Construction Standards"
SL38-92 "Water quality of the project capital works unit grading criteria (7)"
SL239-1999 "dike construction quality assessment and acceptance of"
3, construction preparation
3.1 The contract and design documents for in-depth series of specific conditions of good construction organization design.
3.2 do all the technical preparations, and do a good job, "Stone a flat" Temporary Works, a variety of devices and equipment preparations. Diversion and the introduction of drainage works have been completed.
3.3 Surveying setting has been inspected and accepted, the main measuring points have been laid a solid frame, foundation, dam (dike) lofting body has been set aside by the design settlement.
3.4-site verification of soil aggregates, reserves should be larger than 1.5-2.5 times the required amount. Soil and natural water content meet the design requirements.
3.5 mechanical facilities, test equipment in place, has done Impervious soil material rolling test, based on clean-up has been completed and after acceptance.
4, construction operational requirements
4.1 Excavation of earth material
4.1.1 pit excavation before excavation designated area, remove the roots and prevent facilities rocks
 