箱梁施工作业指导书.doc
箱梁施工作业指导书
针对当前我后张箱梁即将开工之即的各种施工情况,为了控制梁体在预制前后,内在、外在质量能够达到业主的高标准要求。现对箱梁施工队伍技术负责人员就各具体施工环节作如下的作业指导:
一、指导范围
该作业指导书包括后张法20m箱梁的施工、吊运及存放。
二、相关的技术规范
(1)XX高速公路《两阶段施工图设计》
(2)《公路工程国内招标文件范本》
(3)GB1489-98《钢筋砼及热轧带肋钢筋》
(4)GB13013-91《钢筋砼及热轧光圆钢筋》
(5)JTJ041-2000《公路桥涵施工技术规程》
三、各阶段指导内容
1、非预应力钢筋的制做、成型、绑扎
(1)与图核对成品钢筋的钢号、直径、形状、规格尺寸和数量是否正确无误,如有遗漏,应及时纠正、增补,并及时与现场技术负责人取得沟通后方可开始制作。
(2)钢筋的制做为使其在加工成型后满足规范,应针对图纸设计型号、类别分专人专项加工制作。制作时:
a、钢筋的表面应洁净,使用前应将表面油渍、漆皮、鳞锈等清除干净。
b、钢筋应平直,无局部弯折,成盘的钢筋
Box girder work instructions
Post-tensioned box girder for the current I that is all about to start the construction of the body to control the beam before and after the prefabricated, internal and external quality of the owners to achieve high standards. Technical teams are on the box girder for construction of staff on specific aspects of the operation guidance as follows:
A guide scope
The work instructions include 20m post-tensioned box girder construction, lifting and storage.
Second, related technical specifications
(1) XX Highway, "two-stage construction design"
(2) "Highway project template domestic tender documents"
(3) GB1489-98 "reinforced concrete and hot rolled ribbed"
(4) GB13013-91 "reinforced concrete and hot rolled round bar"
(5) JTJ041-2000 "in Bridge Construction" Technical Specification
Third, the contents of each stage guide
1, making non-prestressed reinforcement, molding, banding
(1) finished with the map check the steel reinforcement, diameter, shape, size and quantity specifications are correct and, if missed, should be promptly corrected, updated and timely access and on-site person in charge of communication technology may commence only after production.
(2) reinforcement of the system as to meet the specifications after the molding process should be designed for drawing models, a special category of hand manufacture. Production Time:
a, steel surfaces should be clean, grease the surface before use should, patent leather, scale rust, etc. cleaned.
b, bar should be straight, no local bending into a plate of steel