新村大桥T梁预应力施工方案
一、 概述
新村大桥T梁长度为30m,预应力张拉采用标准号ASTM A416-98,270级,公称直径15.24mm,标准强度1860MPa的低松弛预应力钢绞线做为预应力钢束,钢绞线松弛率为1.15%,锚具为15-6,15-5,15-3型群锚体系,采用波纹管预埋制孔。
二、 预应力钢绞线制作
(1) 钢绞线的运输及保管
预应力钢绞线在运输中或现场使用,应避免造成局部弯曲和折伤,不得抛扔或拖卷材。
现场保管时,下面应垫上石子或方木,上面覆盖雨布防腐蚀。
(2) 钢绞线开盘
钢绞线呈圆盘状运至现场后,先平置在石子垫层木制垫柜上以防泥土、水对钢绞线的腐蚀,四周用直径为5cm的钢管将钢绞线固定,以防拉出散乱,扭曲和伤人。打开钢绞线外包装,抽出钢绞线线头,抽拉时,一边拉,一边放松其扣,否则钢绞线会乱盘,对于有缺陷的部分,必须处理。
(3) 钢绞线的切割与编束
根据图纸设计尺寸,确定料长,采用砂轮锯切断,不得用电弧切割。同一根钢绞线不得焊缝接头,同管道内
Village prestressed beam bridge construction program T
I. Introduction
Village Bridge T Beam length is 30m, prestressed tension of a standard No. ASTM A416-98, 270 level, the nominal diameter of 15.24mm, Standard strength 1860MPa low relaxation prestressed concrete strand as the prestressed steel strand relaxation rate of 1.15%, anchor bolt system for the 15-6,15-5,15-3 type group using the corrugated pipe embedded system holes.
Second, production of prestressed steel strand
(1) strand of the Transport and storage
Prestressed steel strand in the transport or field use, should be bent and folded to avoid local injury, may not throw or toss drag sheet.
On-site storage, the following should be mat side stones or wood, covered with rain deployed corrosion.
(2) strand opening
Strand cylindrical discoid transported to the scene, the first flat stones placed in the wooden cushion pad cabinet to prevent soil, water, corrosion of the steel strand, around the pipe with a diameter of 5cm will strand fixed, to prevent Pull out the scattered, twisted and wounding. Open the outer strand, strand out of thread, pull, the side pull, while easing the buckle, or strand people would drive for a defective part, must be addressed.
(3) strand of the cutting beam and compiled
According to the design size drawings to determine the expected length, with wheel saw cut, not cut with the arc. No weld joints with a steel wire, with the pipeline
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160780次
- Autocad2013 64位32位破解版附带注册机
- 148385次
- 天正建筑8.5破解版
- 144084次
- autocad2012 64位32位 破解版(附注册
- 137477次
- 天正建筑8.2破解版
- 123424次
- autocad2010免费下载(简体中文版)
- 97157次
- CAD2008注册机及使用说明
- 80847次
- 免费农村房屋设计图
- 73852次
- cad图集大全
- 56934次
- 11g101图集全套下载
- 45655次
- 沉井施工方案
- 1654次
- 石方爆破施工方案
- 1531次
- 土方回填施工方案
- 1174次
- 水泥稳定级配碎石基层施工方案
- 983次
- 沉管灌注桩施工方案
- 919次
- 石拱桥工程施工方案
- 773次
- 路基排水工程施工方案
- 732次
- 珠江新城隧道施工方案
- 663次
- 给水管道、消防管道和排风管道安装工程
- 561次
- SPJ30-300型架桥机施工方案图(CAD)
- 525次