新世界花园回迁楼基坑支护施工方案.doc
二、工程概况
(一)建筑结构设计概况
拟建新世界花园回迁楼是一幢集商业和商住为一体的建筑物,地上十四层,局部十层,地下三层。建筑物外观呈“┓”形,回迁楼建筑结构周长约411m,基坑开挖深度-15.5m(决对标高L29.68m),建筑物±0.00=48.18m。设建在南面和东面为地下停车场的1#和2#车道,1#和2#车道进出车库的位置不同,单平面位置在南面和东面相重叠且委员地下三层基槽之外,整改车道共用基础结构外墙,车道净宽3.6m,自南面向东面延伸的车道基地标高约为-4.85m(绝对标高:40.23m)~-13.75m(绝对标高:31.43m)。
(二)建设场地及周围环境状况
北京新世界花园商业小区位于崇文门外大街西侧,东茶食胡同与珠市东大街之间,北临在建的新世界中心二期工程,占地8.7公顷。拟建的新世界花园商业回迁楼位于花园小区的东北角方位。现状地面标高为:43.21~45.52m。拟建的回迁楼周围环境较复杂,除北面和东面为道路无距离较近的建筑物外,其它几面均有临近的建筑物需要保护,其中:在拐角回迁楼的内侧临近与之同时开工的1#住宅楼(基础埋深-3.10m,相当于42.08m),两者结构距离最近处约为3.5m,其它距离在4.2~11.6m范围;南面临近崇文区文化馆的三层群房(其±0.00=43.40m基础底标高-7.04m,相当于38.14m),结构净距离约为9.37m;东临崇文门外大街,设计车道结构外皮距围墙5.1m。基坑的东面
Second, project profiles
(A) Overview of Design of Building Structures
New World Garden Huiqian Lou is a proposed set of commercial and residential buildings as a whole, the ground layer 14, local 10 floors on the ground three. Building appearance "┓" shape, Hui Qianlou week about building structure 411m, excavation depth-15.5m (decision on the level L29.68m), building ± 0.00 = 48.18m. To be built in the south and east for the underground car park of 1 # and 2 # Drive, 1 # and 2 # Drive out the location of the garage, the single-plane location of overlap in the south and east and the members of the underground tank outside the base layer, external rectification Drive shared infrastructure, Drive clear width 3.6m, extending from the south east of the lane for the base level of about-4.85m (absolute elevation: 40.23m) ~-13.75m (absolute elevation: 31.43m).
(B) of the construction site and the surrounding environment
Beijing New World Garden is located in Chongwen district business outside the Avenue west, East cakes and sweetmeats alley between East Street and Pearl City, north in the construction of the New World Centre Phase II, an area of 8.7 hectares. The proposed New World Garden, Garden District business Huiqian Lou in the northeast corner of position. Status surface elevation: 43.21 ~ 45.52m. The proposed Hui Qianlou more complex environment, in addition to the north and east of the road no closer to the building from the outside, several other buildings near the surface are in need of protection, including: the inside near the corner with Huiqian Lou also started a # residential building (basic depth-3.10m, equivalent to 42.08m), the two structures is about the nearest office 3.5m, other distance in the range of 4.2 ~ 11.6m; south near the cultural centers of the three groups, Chongwen District room (the ± 0.00 = 43.40m base bottom elevation-7.04m, equivalent to 38.14m), the structure of net distance of about 9.37m; east Chongwenmen Avenue, away from the wall of the jacket design Drive structure 5.1m. Excavation of the east
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160543次
- Autocad2013 64位32位破解版附带注册机
- 148312次
- 天正建筑8.5破解版
- 144047次
- autocad2012 64位32位 破解版(附注册
- 137474次
- 天正建筑8.2破解版
- 123394次
- autocad2010免费下载(简体中文版)
- 97140次
- CAD2008注册机及使用说明
- 80812次
- 免费农村房屋设计图
- 73732次
- cad图集大全
- 56766次
- 11g101图集全套下载
- 45320次
- 基坑土方开挖专项施工方案
- 1627次
- 土方开挖专项方案
- 1037次
- 基础回填土施工方案
- 658次
- 深基坑支护工程设计技术
- 525次
- 临港新城书院社区三期—2动迁商品住宅
- 498次
- 2004浙G23钻孔灌注桩
- 456次
- 外墙涂料工程分项工程质量技术交底卡
- 442次
- Dj6强夯法、强夯置换法处理地基
- 403次
- 预应力管桩施工地基土隆起的预控措施
- 401次
- 建筑施工手册(第四版)土方与基坑工程
- 400次