YT-HA1 标粉喷桩施工组织设计
一、工程概况
盐城至南通高速公路海安一施工标段位于海安县大公镇和洋蛮河镇境内,本标段路线起点接盐通高速公路(南通市境)东台三施工标段终点(桩号为K71+958.764),起点桩号为K72+038,路线经大公镇东,在K73+082.500处跨越红星河(等外航道),在K74+696处跨越大公-海安农场公路,在大公镇和洋蛮河镇交界处(K77+017.500)跨越北凌河,经洋蛮河镇东,在K81+645.500处跨越洋蛮河(韩洋)至李堡公路,终点在K82+500处接海安二施工标段。本段全线长10.462km。
本标段粉喷桩处理软土地基工程,位于长江河谷平原工程地质区,主要不良地质条件为软土和砂土液化。为了减小工后沉降量,保证路基稳定,解决结构物处跳车等病害,设计采
YT-HA1 standard DJM Construction Design
First, project survey
Yancheng to Nantong expressway construction sections in Hoi Hoi an town and the Ocean County Grand Man Town in the territory of the tenders received route from Salt Expressway (Nantong City in) end of the East China and Taiwan, construction sections (Stake for the K71 +958.764) , from Stake to K72 +038, Route, the Grand Duke Town, across the Red Division in the K73 +082.500 Galaxy (substandard Channel), the K74 +696 office across the Grand - Hai Farm Road, in the town and the ocean Man Town in Grand junction (K77 +017.500) across North Dalinghe by Yang Man Town in the East, across the ocean in the K81 +645.500 Office Man River (Han-yang) to Fort Lee Road, ending at K82 +500 Office Access MSC 2 construction sections. Total length of this paragraph 10.462km.
The tenders DJM soft foundation engineering, engineering geology in the Yangtze River valley plain area, the main adverse geological conditions of the soft soil and sand liquefaction. In order to reduce the settlement after construction to ensure embankment stability, solution structures such as the Jump disease, the design adopted
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160543次
- Autocad2013 64位32位破解版附带注册机
- 148312次
- 天正建筑8.5破解版
- 144047次
- autocad2012 64位32位 破解版(附注册
- 137474次
- 天正建筑8.2破解版
- 123394次
- autocad2010免费下载(简体中文版)
- 97140次
- CAD2008注册机及使用说明
- 80812次
- 免费农村房屋设计图
- 73732次
- cad图集大全
- 56766次
- 11g101图集全套下载
- 45320次
- 基坑土方开挖专项施工方案
- 1627次
- 土方开挖专项方案
- 1037次
- 基础回填土施工方案
- 658次
- 深基坑支护工程设计技术
- 525次
- 临港新城书院社区三期—2动迁商品住宅
- 498次
- 2004浙G23钻孔灌注桩
- 456次
- 外墙涂料工程分项工程质量技术交底卡
- 442次
- Dj6强夯法、强夯置换法处理地基
- 403次
- 预应力管桩施工地基土隆起的预控措施
- 401次
- 建筑施工手册(第四版)土方与基坑工程
- 400次