开关、插座安装工程技术交底-建筑安装.doc
一、 施工准备
(一) 作业条件
1、 各种管路、盒子已经敷设完毕,损坏的盒子已换掉。
2、 盒子缩进装饰面超过20mm的已加套盒,且套盒与原盒有可靠的措施,拔插时不能将套盒与面板一起拔出。
3、 盒子缩进装饰面不够20mm已用高强度水泥砂浆外口抹平齐,内口抹方正。
4、 线路的导线已穿完,并已对各支路完成绝缘摇测。
5、 墙面抹灰、油漆及壁纸等内装修工作均已完成。
为防止土建施工污染插座面板,水泥地面、铺砖地面、水磨石、大理石地
First, construction preparation
(A) Operating conditions
1, various pipes, boxes have been completed the laying of the damaged box has been replaced.
2, box decorative surface indentation that has added more than 20mm Packing carton, and Packing carton with the original box with reliable measures, plug Packing carton with the panel, was unable to pull together.
3, box decorative surface indentation 20mm has enough high-strength cement mortar smoothing Qi of foreign population, which I wipe Founder.
4, the line had been wearing complete wire and insulation has been completed on each branch shake test.
5, wall plaster, paint and wallpaper and other interior decoration work had been completed.
To prevent pollution of socket panel civil construction, cement floors, tiling floors, terrazzo, marble