一、施工前控制要点
1、 审核承包单位的技术资质证明文件、专业人员的资格证上岗证。
2、 审核承包单位的施工方案施工组织设计
3、 审核施工测量成果报验表、复查桩位、控制标高等。
4、 检查进入现场的成品桩,接桩用电焊条等产品质量及出厂技术质量合格证书、品种、类型、规格(桩径、管壁厚、桩长强度、质量(外观应符合设计要求和国家现行标准《先张法预应力砼管桩》GB13476-92的规定及验收规范的规定。
5、 审查打桩设备的技术性能资料是否满足工程实际的需要。如选择柴油打桩锤,应考虑如下问题:
(1) 要保证单桩承载力能达到设计要求(国内经验,每个型号的柴油锤,其最大成桩能力(单桩极限承载力,约为100倍的型号数(KN),如D45型,最多可打极限承载力4500Kpa)。
(2) 要考虑桩的入土深度即桩的自重大小(凭经验按锤重与桩重的比例,对一般土质取0.5,若软土较厚可取 0.4)。
(3) 要根据土质、岩性和布桩状况来选择锤型,每根桩的总击数宜在1500击以内。
(4) 要保证冲击压应力不超过桩身砼极限强度的50%。
First, control points before construction
1, review the technical qualifications of contractors proof of professional qualification certificates work license.
2, review contractor's construction program and construction organization design.
3, audit inspection table construction survey results, review pile and control the elevation so.
4, checking into the site of the finished pile, the pile electric welding techniques such as product quality and factory quality certification, variety, type, specifications (length, diameter, pipe wall thickness, pile length and intensity, quality (appearance should be consistent with design requirements and the state the current standard of "first Prestressed Concrete Pipe" GB13476-92 requirements and acceptance requirements.
5, review the technical performance data piling equipment meets the engineering requirements. If you choose to diesel hammer, shall consider the following questions:
(1) To ensure the bearing capacity to meet the design requirements (domestic experience, each model of diesel hammer, the maximum pile capacity (single pile ultimate bearing capacity, about 100 times the model number (KN), such as the D45 type up to play ultimate capacity 4500Kpa).
(2) to consider the pile at a depth of the pile of dead weight size (rule of thumb by weight of hammer and pile weight ratio of the average soil is 0.5, if the thicker soft desirable 0.4).
(3) according to soil, rock and pile conditions to select hammer type, each pile in the 1500 general strike should hit within a few.
(4) To ensure that the impact of stress does not exceed the ultimate strength of concrete pile 50%.
 